United States › Grid › Interconnection queues › California

ONSHORE WIND · CAISO

Rising Tree Wind Farm (Fka Homestead Wind Farm)

Rising Tree Wind Farm (Fka Homestead Wind Farm) is a 198 MW onshore wind request built and operating in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Mar 2007 (completed)
  2. ConsentedSep 2014 (completed)
  3. Construction (completed)
  4. OperatingJun 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
188
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Windhub Substation 230kV
Location
Kern County, California
Technology
Wind: 198 MW
Total requested
198 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
23 March 2007
Agreement signed
5 September 2014
Proposed online date
December 2013
Came online
June 2015

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem