Patel Brothers Energy Storage System

Patel Brothers Energy Storage System is a 0.3 MW battery storage request withdrawn in the PJM interconnection queue, in Pickaway County, Ohio, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2021 (completed)
  2. Withdrawn / abandonedJan 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-135
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Hoffman Estates 12.5 kV
Location
Pickaway County, Ohio
Technology
Battery: 0.3 MW
Total requested
0.3 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
4 February 2021
Proposed online date
April 2022
Withdrawn
January 2022

Location

Marker shows the centre of Pickaway County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Pickaway County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem