United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Sandine Solar

Sandine Solar is a 30.0 MW solar request withdrawn in the ERCOT interconnection queue, in Cottle County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2017 (completed)
  2. Withdrawn / abandonedMar 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0022
Grid region
ERCOT (Texas)
Developer
Innovative Solar
Connection point (POI)
tap 138kV 6135 Paducah - 6320 Tardis
Location
Cottle County, Texas
Technology
Solar: 30.0 MW
Total requested
30.0 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
9 August 2017
Proposed online date
May 2022
Withdrawn
March 2021

Location

Marker shows the centre of Cottle County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Cottle County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem