United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Alamo Springs Solar 3

Alamo Springs Solar 3 is a 158 MW solar request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedMar 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1254
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
PG&E Arco Substation 70 kV
Location
Kern County, California
Technology
Solar: 158 MW
Total requested
158 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
2 May 2016
Proposed online date
July 2019
Withdrawn
March 2017

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem