SOLAR · ERCOT

Juno Solar (Phase I)

Juno Solar (Phase I) is a 166 MW solar request built and operating in the ERCOT interconnection queue, in Borden County, Texas.

Queue statusOperating
  1. PlanningQueued Aug 2018 (completed)
  2. ConsentedDec 2018 (completed)
  3. Construction (completed)
  4. OperatingMay 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0026
Grid region
ERCOT (Texas)
Developer
SE Juno, LLC
Connection point (POI)
59906 Long Draw 138 kV
Location
Borden County, Texas
Technology
Solar: 166 MW
Total requested
166 MW
Study phase
IA
Queue status
Operational
Entered queue
13 August 2018
Agreement signed
22 December 2018
Proposed online date
May 2021
Came online
May 2021

Location

Marker shows the centre of Borden County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Borden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem