United States βΊ Grid βΊ Interconnection queues βΊ Maryland
SOLAR Β· PJMSolar project AB1-066, Frederick County
Solar project AB1-066, Frederick County is a 19.8 MW solar request withdrawn in the PJM interconnection queue, in Frederick County, Maryland, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2015 (completed)
- Withdrawn / abandonedMar 2016 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AB1-066
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Lime Kiln-Aqueduct 34.5kV
- Location
- Frederick County, Maryland
- Technology
- Solar: 19.8 MW
- Total requested
- 19.8 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 August 2015
- Proposed online date
- December 2016
- Withdrawn
- March 2016
Location
Marker shows the centre of Frederick County; the queue data does not give exact sites.
Other requests in Frederick County
- Solar + storage project AH2-262, Frederick CountySolar + storage Β· 17.0 MW Β· in study
- Bedington Energy FacilitySolar Β· 100 MW Β· suspended
- Legore Bridge Solar Center FacilitySolar Β· 20.0 MW Β· built
- Biggs Ford Solar FacilitySolar Β· 15.0 MW Β· built
- Mount St. Mary's PV ParkSolar Β· 14.0 MW Β· built
- Frederick Road SolarSolar Β· 9.0 MW Β· built
- Reichs LFOther Β· 2.0 MW Β· built
- Gas project G50, Frederick CountyGas Β· 910 MW Β· withdrawn
- Gas project G00_W39, Frederick CountyGas Β· 668 MW Β· withdrawn
- Catoctin CCGas Β· 640 MW Β· withdrawn
- Gas project E05_W25, Frederick CountyGas Β· 620 MW Β· withdrawn
- Solar project AC1-139, Frederick CountySolar Β· 102 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem