Solar project AG2-253, Trumbull County

Solar project AG2-253, Trumbull County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Trumbull County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-253
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Dilworth 69 kV III
Location
Trumbull County, Ohio
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
18 March 2021
Proposed online date
January 2023
Withdrawn
December 2024

Location

Marker shows the centre of Trumbull County; the queue data does not give exact sites.