ONSHORE WIND · NYISO

Galloo Island Wind

Galloo Island Wind is a 110 MW onshore wind request withdrawn in the NYISO interconnection queue, in Oswego County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2014 (completed)
  2. Withdrawn / abandonedFeb 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
468
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Apex Clean Energy LLC
Connection point (POI)
Hammermill - Wine Creek 115kV
Location
Oswego County, New York
Technology
Wind: 110 MW
Total requested
110 MW
Queue status
Withdrawn
Entered queue
30 December 2014
Withdrawn
February 2021

Location

Marker shows the centre of Oswego County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Oswego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem