πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Wisconsin

ONSHORE WIND Β· MISO

Onshore wind project G724, Dane County

Onshore wind project G724, Dane County is a 99.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Dane County, Wisconsin.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2007 (completed)
  2. Withdrawn / abandonedApr 2009 (project stopped here)
  3. ConsentedApr 2009 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G724
Grid region
MISO (Midcontinent)
Connection point (POI)
North Madison - West Middleton 138 kV
Location
Dane County, Wisconsin
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
8 January 2007
Agreement signed
8 April 2009
Proposed online date
September 2008
Withdrawn
April 2009

Location

Marker shows the centre of Dane County; the queue data does not give exact sites.

Power plants in Wisconsin Β· Transmission lines in Wisconsin

Other requests in Dane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem