United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

COAL Β· SOUTHEAST

Coal project 31, Taylor County

Coal project 31, Taylor County is a 850 MW coal request withdrawn in the Southeast interconnection queue, in Taylor County, Florida, connecting to Duke Energy Florida.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2005 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
31
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Masked
Connection point (POI)
Perry Substation
Location
Taylor County, Florida
Technology
Coal: 850 MW
Total requested
850 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
21 October 2005
Proposed online date
June 2012

Location

Marker shows the centre of Taylor County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Taylor County