Arco Solar 1 Project

Arco Solar 1 Project is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2009 (completed)
  2. Withdrawn / abandonedSep 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
514
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Arco Substation 69kV bus
Location
Kern County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 July 2009
Proposed online date
October 2016
Withdrawn
September 2014

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.