United States › Grid › Interconnection queues › California

SOLAR · CAISO

Freshwater Solar Generating Facility (Fka Sweetwater PV 20MVA Solar Generating Facility)

Freshwater Solar Generating Facility (Fka Sweetwater PV 20MVA Solar Generating Facility) is a 20.0 MW solar request built and operating in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Oct 2009 (completed)
  2. ConsentedAug 2013 (completed)
  3. Construction (completed)
  4. OperatingJan 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
529
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Corcoran- Kingsburg #1 115kV line
Location
Kings County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Operational
Entered queue
19 October 2009
Agreement signed
27 August 2013
Proposed online date
August 2013
Came online
January 2016

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kings County