United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Other interconnection queue in the USA (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3011.0 GW
Active in queue11.0 GW30 requests
Agreement signed8.0 MW2 requests
Withdrawn5212.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

30 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project G0695, Crook County
Other
3,600 MWIn study Crook, ORWest Sep 2021target 2028
Other project G0675, Crook County
Other
1,800 MWIn study Crook, ORWest Mar 2021target 2029
Other project 103, Apache County
Other
768 MWIn study Apache, AZWest Nov 2021target 2024
Other project 110, Garfield County
Other
560 MWIn study Garfield, WAWest Jan 2021target 2025
Other project 107, Pima County
Other
400 MWIn study Pima, AZWest Dec 2021target 2024
Other project 106, Pima County
Other
320 MWIn study Pima, AZWest Dec 2021target 2024
Other project 607, Sweetwater County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWPaused / redesign Sweetwater, WYWest Jun 2021target 2025
Other project G0693, Crook County
Other
300 MWIn study Crook, ORWest Sep 2021target 2025
SP Jaguar BESS
Other Β· PP Jaguar BESS LLC
300 MWPaused / redesign Mclennan, TXERCOT Mar 20212025
Other project 608, Sweetwater County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWPaused / redesign Sweetwater, WYWest Jun 2021target 2025
Other project 100, Pima County
Other
250 MWIn study Pima, AZWest Oct 2021target 2024
Other project 95, Apache County
Other
250 MWIn study Apache, AZWest Jun 2021target 2024
Other project 98, Pinal County
Other
241 MWIn study Pinal, AZWest Sep 2021target 2025
Masroor Storage
Other Β· Masroor Energy Storage LLC
203 MWPaused / redesign Fannin, TXERCOT Nov 2021target 2025
Snap Jaw BESS
Other Β· Moccasin Pointe Grid, LLC
201 MWPaused / redesign Harris, TXERCOT Apr 2021target 2028
Other project 110, Pima County
Other Β· TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Other project 109, Pima County
Other Β· TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Other project 609, Sweetwater County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
200 MWPaused / redesign Sweetwater, WYWest Jun 2021target 2025
Other project 108, Pima County
Other Β· TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Heartfield Storage
Other Β· Belltown Power Texas
152 MWPaused / redesign Hidalgo, TXERCOT Sep 2021target 2023
Fort Duncan BESS
Other Β· Fort Duncan BESS LLC
106 MWPaused / redesign Maverick, TXERCOT Aug 20212025
Surplus; J878
Other
60.0 MWIn study MISO Apr 20212024
Other project GI-2021-144, Imperial County
Other
28.0 MWIn study Imperial, CAWest Mar 2021target 2028
Other project AH2-006, Pickaway County
Other
14.2 MWIn study Pickaway, OHPJM Oct 2021target 2024
Other project AH2-007, Fayette County
Other
10.1 MWIn study Fayette, OHPJM Oct 2021target 2024
Battery addition
Other
6.7 MWAgreement signed Franklin, MAISO-NE Aug 2021target 2027
Other project Q394, Maricopa County
Other
5.0 MWIn study Maricopa, AZWest Mar 2021target 2021
Other project AH2-001, Susquehanna County
Other
3.6 MWIn study Susquehanna, PAPJM Oct 2021target 2023
Other project G0710, Flathead County
Other
1.6 MWIn study Flathead, MTWest Nov 2021target 2022
Other project Company MN, Lyon County
Other
1.3 MWAgreement signed Lyon, NVWest Dec 2021target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)