Withdrawn queue requests in West Virginia (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown161,555 MW
Active in queue403 MW4 requests
Agreement signed0.0 MW0 requests
Withdrawn161,555 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project AI1-202, Grant County
Other
450 MWWithdrawn / abandoned Grant, WVPJM Sep 2022target 2026
Solar + storage project AH2-424, Randolph County
Solar + storage
120 MWWithdrawn / abandoned Randolph, WVPJM Mar 2022target 2025
Solar project AI1-014, Berkeley County
Solar
100 MWWithdrawn / abandoned Berkeley, WVPJM Apr 2022target 2026
Battery storage project AH2-278, Kanawha County
Battery storage
100 MWWithdrawn / abandoned Kanawha, WVPJM Mar 2022target 2024
Solar + storage project AH2-192
Solar + storage
95.0 MWWithdrawn / abandoned WVPJM Mar 2022target 2024
Solar + storage project AH2-209, Kanawha County
Solar + storage
95.0 MWWithdrawn / abandoned Kanawha, WVPJM Mar 2022target 2024
Solar + storage project AH2-191
Solar + storage
95.0 MWWithdrawn / abandoned WVPJM Mar 2022target 2024
Solar + storage project AH2-207
Solar + storage
85.0 MWWithdrawn / abandoned WVPJM Mar 2022target 2024
Solar project AI1-116
Solar
70.0 MWWithdrawn / abandoned WVPJM Sep 2022target 2024
Solar + storage project AH2-193
Solar + storage
70.0 MWWithdrawn / abandoned WVPJM Mar 2022target 2024
Solar + storage project AH2-255, Preston County
Solar + storage
70.0 MWWithdrawn / abandoned Preston, WVPJM Mar 2022target 2025
Solar project AH2-260, Preston County
Solar
70.0 MWWithdrawn / abandoned Preston, WVPJM Mar 2022target 2026
Solar project AI1-117
Solar
60.0 MWWithdrawn / abandoned WVPJM Sep 2022target 2024
Solar + storage project AI1-096
Solar + storage
42.0 MWWithdrawn / abandoned WVPJM Aug 2022target 2027
Battery storage project AH2-261, Preston County
Battery storage
28.0 MWWithdrawn / abandoned Preston, WVPJM Mar 2022target 2026
Solar project AH2-134, Kanawha County
Solar
5.0 MWWithdrawn / abandoned Kanawha, WVPJM Mar 2022target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)