Completed queue projects in West Virginia

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown362,608 MW
Active in queue6,900 MW41 requests
Agreement signed1,291 MW11 requests
Withdrawn16121.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

36 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Longview ST1
Coal
600 MWOperating Monongalia, WVPJM May 20012008
Greenland Gap WF
Onshore wind
300 MWOperating Grant, WVPJM Jan 20022007
Oak Grove CT1 & CT2
Gas
300 MWOperating Pleasants, WVPJM Jan 19992002
Beech Ridge / Field Mtn WF
Wind + storage
186 MWOperating Greenbrier, WVPJM Jul 20042007
Black Rock Wind
Onshore wind
110 MWOperating Mineral, WVPJM Mar 20182021
New Creek Mountain Wind Farm
Onshore wind
103 MWOperating Mineral, WVPJM Jan 20082016
Longview ST1
Coal
100 MWOperating Monongalia, WVPJM Jul 20062010
Laurel Mountain WF
Onshore wind
97.6 MWOperating Barbour, WVPJM Jan 20062008
Backbone WF
Onshore wind
90.0 MWOperating Tucker, WVPJM Nov 19992003
Pinnacle WF
Onshore wind
85.0 MWOperating Mineral, WVPJM Jan 20052011
Blake Solar
Solar
80.0 MWOperating Jefferson, WVPJM Oct 20192024
Greenland Gap WF
Onshore wind
60.0 MWOperating Grant, WVPJM Jul 20032007
Hawks Nest Hydro
Hydro
54.2 MWOperating Fayette, WVPJM Jan 20072009
Oak Grove CT1 & CT2
Gas
54.0 MWOperating Pleasants, WVPJM May 20012003
Beech Ridge Wind Farm
Onshore wind
50.6 MWOperating Greenbrier, WVPJM Oct 20152020
Mount Storm Unit 2
Coal
38.0 MWOperating Grant, WVPJM Jul 20072011
Mount Storm Unit 1
Coal
38.0 MWOperating Grant, WVPJM Jul 20072013
Willow Island Hydro Generation Project
Hydro
36.4 MWOperating Wetzel, WVPJM Jul 20072015
John Amos Generating Plant Unit No. 3
Coal
36.0 MWOperating Putnam, WVPJM Feb 20132015
Harrison 1, 2, 3
Coal
35.0 MWOperating Harrison, WVPJM Mar 20022004
Laurel Mountain BT
Battery storage
27.4 MWOperating Barbour, WVPJM Jul 20102011
Mountaineer #1
Coal
20.0 MWOperating Mason, WVPJM May 20052005
Capon Bridge Solar
Solar
20.0 MWOperating Hampshire, WVPJM Sep 20182024
Big Sandy Peaker Plant
Gas
18.0 MWOperating Wayne, WVPJM Oct 20172020
Oak Grove 138kV
Gas
13.7 MWOperating Pleasants, WVPJM Aug 20122014
Longview Power
Coal
10.0 MWOperating Monongalia, WVPJM Oct 20162018
Belleville Hydroelectric Plant
Hydro
7.0 MWOperating Wood, WVPJM Apr 20132014
Willow Island Hydro Generation Project
Hydro
6.8 MWOperating Pleasants, WVPJM Mar 20122015
Big Sandy Peaker Plant
Gas
6.0 MWOperating Wayne, WVPJM Oct 20042005
Beech Ridge Wind Farm
Onshore wind
5.0 MWOperating Greenbrier, WVPJM Aug 20182020
Kanawna River #2
Coal
5.0 MWOperating Kanawha, WVPJM Jan 20072007
Kanawna River #1
Coal
5.0 MWOperating Kanawha, WVPJM Jan 20072007
Seven Islands Environmental Solutions, LLC
Other
3.2 MWOperating WVPJM Oct 20152017
Charleston Clean Energy
Other
3.2 MWOperating Kanawha, WVPJM Jan 20132019
Balls Gap Battery Facility
Battery storage
2.0 MWOperating Cabell, WVPJM Aug 20152017
Charlston LF
Other
2.0 MWOperating Kanawha, WVPJM Apr 20092010

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)