🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › West Virginia

ONSHORE WIND · PJM

Pinnacle WF

Pinnacle WF is a 85.0 MW onshore wind request built and operating in the PJM interconnection queue, in Mineral County, West Virginia, connecting to APS.

Queue statusOperating
  1. PlanningQueued Jan 2005 (completed)
  2. ConsentedFeb 2010 (completed)
  3. Construction (completed)
  4. OperatingNov 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
N47
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Beryl 138kV
Location
Mineral County, West Virginia
Technology
Wind: 85.0 MW
Total requested
85.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
31 January 2005
Agreement signed
3 February 2010
Proposed online date
December 2011
Came online
November 2011

Location

Marker shows the centre of Mineral County; the queue data does not give exact sites.

Power plants in West Virginia · Transmission lines in West Virginia

Other requests in Mineral County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem