Withdrawn queue requests in Virginia (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown25596 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn25596 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

25 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Tidewater Solar Projects
Solar
91.0 MWWithdrawn / abandoned Southampton, VAPJM Dec 2015target 2022
Solar project AB1-070, Greensville County
Solar
80.0 MWWithdrawn / abandoned Greensville, VAPJM Sep 2015target 2017
Fort Powhatan Solar
Solar
80.0 MWWithdrawn / abandoned Prince George, VAPJM Apr 2015target 2021
Solar project AB1-054, Southampton County
Solar
60.0 MWWithdrawn / abandoned Southampton, VAPJM Aug 2015target 2018
Solar project AA2-154, Southampton County
Solar
20.0 MWWithdrawn / abandoned Southampton, VAPJM Apr 2015target 2015
Battery storage project AA2-129, Accomack County
Battery storage
20.0 MWWithdrawn / abandoned Accomack, VAPJM Apr 2015target 2016
Solar project AA2-163, Sussex County
Solar
20.0 MWWithdrawn / abandoned Sussex, VAPJM Apr 2015target 2015
Charles City Solar
Solar
20.0 MWWithdrawn / abandoned VAPJM Oct 2015target 2019
Montross Solar
Solar
20.0 MWWithdrawn / abandoned Westmoreland, VAPJM Jul 2015target 2020
Chesapeake Solar
Solar
20.0 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Apr 2015target 2016
Solar project AB1-028, Southampton County
Solar
20.0 MWWithdrawn / abandoned Southampton, VAPJM Jul 2015target 2016
Solar project AA2-158, Louisa County
Solar
20.0 MWWithdrawn / abandoned Louisa, VAPJM Apr 2015target 2015
Solar project AB1-097, Rockingham County
Solar
20.0 MWWithdrawn / abandoned Rockingham, VAPJM Oct 2015target 2017
Solar project AA2-087, Southampton County
Solar
20.0 MWWithdrawn / abandoned Southampton, VAPJM Mar 2015target 2016
Gas project AB1-117, Fluvanna County
Gas
17.3 MWWithdrawn / abandoned Fluvanna, VAPJM Oct 2015target 2016
Stevensburg Solar
Solar
15.0 MWWithdrawn / abandoned VAPJM Oct 2015target 2019
Solar project AB1-159, Surry County
Solar
10.0 MWWithdrawn / abandoned Surry, VAPJM Oct 2015target 2017
Solar project AB1-155, Surry County
Solar
10.0 MWWithdrawn / abandoned Surry, VAPJM Oct 2015target 2017
Solar project AB1-067, Orange County
Solar
10.0 MWWithdrawn / abandoned Orange, VAPJM Aug 2015target 2016
Solar project AB1-059, Hanover County
Solar
5.0 MWWithdrawn / abandoned Hanover, VAPJM Aug 2015target 2017
Saltville-Holston 34.5kV Solar Facility
Solar
5.0 MWWithdrawn / abandoned Smyth, VAPJM Dec 2015target 2017
Saltville-Holston 34.5kV Solar Facility
Solar
5.0 MWWithdrawn / abandoned Smyth, VAPJM Dec 2015target 2017
Boykins Solar
Solar
4.5 MWWithdrawn / abandoned Southampton, VAPJM Mar 2015target 2017
Battery storage project AB1-022, Louisa County
Battery storage
2.0 MWWithdrawn / abandoned Louisa, VAPJM Jul 2015target 2017
Other project AA2-185, Prince William County
Other
1.6 MWWithdrawn / abandoned Prince William, VAPJM Apr 2015target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)