United States βΊ Grid βΊ Interconnection queues βΊ Virginia
OTHER Β· PJMOther project AA2-185, Prince William County
Other project AA2-185, Prince William County is a 1.6 MW other request withdrawn in the PJM interconnection queue, in Prince William County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2015 (completed)
- Withdrawn / abandonedSep 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AA2-185
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Independent Hill 115kV
- Location
- Prince William County, Virginia
- Technology
- Other: 1.6 MW
- Total requested
- 1.6 MW
- Service type
- Energy only (ERIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 30 April 2015
- Proposed online date
- January 2016
- Withdrawn
- September 2015
Location
Marker shows the centre of Prince William County; the queue data does not give exact sites.
Other requests in Prince William County
- Battery storage project AI2-231, Prince William CountyBattery storage Β· 120 MW Β· in study
- Battery storage project AH2-034, Prince William CountyBattery storage Β· 100 MW Β· in study
- Battery storage project AH2-035, Prince William CountyBattery storage Β· 100 MW Β· in study
- Battery storage project AH2-032, Prince William CountyBattery storage Β· 60.0 MW Β· in study
- Battery storage project AH2-033, Prince William CountyBattery storage Β· 60.0 MW Β· in study
- Battery storage project AH2-061, Prince William CountyBattery storage Β· 55.0 MW Β· in study
- Battery storage project AH2-060, Prince William CountyBattery storage Β· 55.0 MW Β· in study
- Battery storage project AH2-059, Prince William CountyBattery storage Β· 30.0 MW Β· in study
- Battery storage project AH2-058, Prince William CountyBattery storage Β· 30.0 MW Β· in study
- Reid Energy CenterBattery storage Β· 20.0 MW Β· in study
- Railroad Energy CenterBattery storage Β· 20.0 MW Β· in study
- Bethlehem Energy CenterBattery storage Β· 20.0 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem