United States β€Ί Grid β€Ί Interconnection queues β€Ί Vermont

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Vermont

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown14880 MW
Active in queue129 MW5 requests
Agreement signed90.0 MW3 requests
Withdrawn602,202 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
VT Yankee Nuclear Power Station Upgrade7
Nuclear
642 MWOperating Windham, VTISO-NE Dec 2002target 2006
Kingdom Community Wind
Onshore wind
61.5 MWOperating Orleans, VTISO-NE Sep 2009target 2012
Sheffield Wind Project
Onshore wind
40.0 MWOperating Caledonia, VTISO-NE Aug 2006target 2011
Vernon Repowering
Hydro
32.0 MWOperating Windham, VTISO-NE Jul 2006target 2008
Deerfield Wind Project
Onshore wind
30.0 MWOperating Bennington, VTISO-NE Sep 2014target 2019
VPPSA Swanton Gas Turbine #1
Gas
21.0 MWOperating Franklin, VTISO-NE Aug 2007target 2010
Coolidge Solar
Solar
19.9 MWOperating Windsor, VTISO-NE Sep 2015target 2018
Georgia Mountain Community Wind
Onshore wind
10.0 MWOperating Chittenden, VTISO-NE May 2010target 2012
GMP Essex Diesel
Other
8.0 MWOperating Chittenden, VTISO-NE Oct 2007target 2007
Moretown Landfill
Other
4.8 MWOperating Washington, VTISO-NE Nov 2007target 2008
Proctor Hydroelectric Station Uprate
Hydro
3.2 MWOperating Rutland, VTISO-NE Mar 2015target 2015
Kingdom Community Wind Increase (see Q311)
Onshore wind
3.1 MWOperating Orleans, VTISO-NE May 2011target 2012
Vernon Station Incremental Capacity Increase
Hydro
2.9 MWOperating Windham, VTISO-NE Apr 2018target 2019
Huntington Falls 2017 Upgrades
Hydro
1.6 MWOperating Chittenden, VTISO-NE Apr 2016target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)