United States โ€บ Grid โ€บ Interconnection queues โ€บ Pennsylvania

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Pennsylvania (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2466,662 MW
Active in queue1,339 MW36 requests
Agreement signed855 MW27 requests
Withdrawn2466,662 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

246 requests ยท page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AF2-411, Clinton County
Battery storage
300 MWWithdrawn / abandoned Clinton, PAPJM Mar 2020target 2023
Beech Hollow Solar
Solar
215 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2020target 2028
Solar project AF2-062, Mckean County
Solar
200 MWWithdrawn / abandoned Mckean, PAPJM Jan 2020target 2023
Firefly Solar
Solar
200 MWWithdrawn / abandoned Lawrence, PAPJM Mar 2020target 2026
Solar + storage project AG1-489, Lawrence County
Solar + storage
175 MWWithdrawn / abandoned Lawrence, PAPJM Sep 2020target 2023
Solar project AG1-060, Schuylkill County
Solar ยท ANTHRACITE RIDGE LLC
175 MWWithdrawn / abandoned Schuylkill, PAPJM Jul 2020target 2022
Battery storage project AF2-195, York County
Battery storage
172 MWWithdrawn / abandoned York, PAPJM Mar 2020target 2022
Mainesburg ESS
Battery storage ยท Juno Power Management LLC
130 MWWithdrawn / abandoned Tioga, PANYISO Jun 2020
Solar + storage project AG1-490, Mercer County
Solar + storage
125 MWWithdrawn / abandoned Mercer, PAPJM Sep 2020target 2023
Battery storage project AG1-248, York County
Battery storage
119 MWWithdrawn / abandoned York, PAPJM Sep 2020target 2022
Battery storage project AF2-197, Bradford County
Battery storage
101 MWWithdrawn / abandoned Bradford, PAPJM Mar 2020target 2022
Battery storage project AF2-412, Tioga County
Battery storage ยท Elk Run LLC
100 MWWithdrawn / abandoned Tioga, PAPJM Mar 2020target 2022
Solar project AG1-059, Westmoreland County
Solar
100 MWWithdrawn / abandoned Westmoreland, PAPJM Jul 2020target 2023
Battery storage project AG1-465, York County
Battery storage
100 MWWithdrawn / abandoned York, PAPJM Sep 2020target 2025
Solar + storage project AG1-549, Armstrong County
Solar + storage ยท Plum Creek Energy, LLC
100 MWWithdrawn / abandoned Armstrong, PAPJM Sep 2020target 2022
Battery storage project AG1-262, Northampton County
Battery storage
85.0 MWWithdrawn / abandoned Northampton, PAPJM Sep 2020target 2022
Battery storage project AF2-213, York County
Battery storage
81.2 MWWithdrawn / abandoned York, PAPJM Mar 2020target 2022
Solar project AF2-164, Venango County
Solar ยท Heartland Solar LLC
80.0 MWWithdrawn / abandoned Venango, PAPJM Mar 2020target 2023
Battery storage project AF2-406, Bradford County
Battery storage ยท Juno Power Management LLC
75.0 MWWithdrawn / abandoned Bradford, PAPJM Mar 2020target 2022
Solar project AF2-261, Luzerne County
Solar
75.0 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2020target 2023
Solar project AF2-330, Cambria County
Solar
70.0 MWWithdrawn / abandoned Cambria, PAPJM Mar 2020target 2022
Spring Run Solar
Solar
70.0 MWWithdrawn / abandoned Fulton, PAPJM Feb 2020target 2030
Solar project AF2-253, Lawrence County
Solar
70.0 MWWithdrawn / abandoned Lawrence, PAPJM Mar 2020target 2022
Solar project AG1-420, Butler County
Solar
70.0 MWWithdrawn / abandoned Butler, PAPJM Sep 2020target 2023
Solar + storage project AG1-474, Centre County
Solar + storage
70.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2020target 2024
Solar project AG1-504, Luzerne County
Solar
68.0 MWWithdrawn / abandoned Luzerne, PAPJM Sep 2020target 2023
Solar project AF2-227, Northampton County
Solar
63.8 MWWithdrawn / abandoned Northampton, PAPJM Mar 2020target 2023
Solar project AF2-228, York County
Solar
61.0 MWWithdrawn / abandoned York, PAPJM Mar 2020target 2023
Solar project AF2-176, Mercer County
Solar ยท Sanderson Solar LLC
60.0 MWWithdrawn / abandoned Mercer, PAPJM Mar 2020target 2022
Solar project AG2-008, Erie County
Solar ยท Blatche Solar, LLC
60.0 MWWithdrawn / abandoned Erie, PAPJM Oct 2020target 2023
Solar project AF2-381, Somerset County
Solar ยท Panther Run Solar, LLC
60.0 MWWithdrawn / abandoned Somerset, PAPJM Apr 2020target 2023
Battery storage project AG1-485, Allegheny County
Battery storage
55.0 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2020target 2024
Upper Paxton Solar
Solar
55.0 MWWithdrawn / abandoned Dauphin, PAPJM Jan 2020target 2027
Solar project AF2-052, Mckean County
Solar
55.0 MWWithdrawn / abandoned Mckean, PAPJM Jan 2020target 2023
Solar project AG1-457, Somerset County
Solar
54.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2020target 2023
Solar project AG1-355, Somerset County
Solar
54.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2020target 2023
Solar + storage project AG1-473, Huntingdon County
Solar + storage ยท North Corners Energy, LLC
53.9 MWWithdrawn / abandoned Huntingdon, PAPJM Sep 2020target 2024
Solar project AF2-145, Lycoming County
Solar
51.0 MWWithdrawn / abandoned Lycoming, PAPJM Mar 2020target 2021
Solar project AF2-331, Montour County
Solar
50.0 MWWithdrawn / abandoned Montour, PAPJM Mar 2020target 2023
Solar project AF2-056, Schuylkill County
Solar ยท Locust Ridge Solar LLC
50.0 MWWithdrawn / abandoned Schuylkill, PAPJM Jan 2020target 2023
Solar project AF2-051, Crawford County
Solar
50.0 MWWithdrawn / abandoned Crawford, PAPJM Jan 2020target 2023
Battery storage project AG1-463, Mercer County
Battery storage
50.0 MWWithdrawn / abandoned Mercer, PAPJM Sep 2020target 2024
Solar project AF2-439, Adams County
Solar
50.0 MWWithdrawn / abandoned Adams, PAPJM Mar 2020target 2023
Nuclear project AF2-315, Luzerne County
Nuclear
50.0 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2020target 2020
Mountain Trail Solar
Solar
50.0 MWWithdrawn / abandoned Berks, PAPJM Sep 2020target 2028
Nuclear project AF2-251, Luzerne County
Nuclear
50.0 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2020target 2020
Solar project AF2-332, Montour County
Solar
50.0 MWWithdrawn / abandoned Montour, PAPJM Mar 2020target 2023
Solar project AF2-262, Luzerne County
Solar
45.0 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2020target 2023
Solar project AF2-323, Crawford County
Solar
44.0 MWWithdrawn / abandoned Crawford, PAPJM Mar 2020target 2022
Victory Solar
Solar
44.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2020target 2026
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)