United States โบ Grid โบ Interconnection queues โบ Pennsylvania
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Pennsylvania (2015 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project AB1-003, Indiana County Gas |
1,474 MW | Withdrawn / abandoned |
| Gas project AA2-109, Lancaster County Gas |
1,100 MW | Withdrawn / abandoned |
| Gas project AB1-153, Adams County Gas |
1,062 MW | Withdrawn / abandoned |
| Gas project AA2-182, Snyder County Gas |
1,030 MW | Withdrawn / abandoned |
| Beech Hollow Energy Center Gas |
1,025 MW | Withdrawn / abandoned |
| Gas project AB1-175, Clearfield County Gas |
989 MW | Withdrawn / abandoned |
| Gas project AB1-151, Wayne County Gas |
575 MW | Withdrawn / abandoned |
| Gas project AA2-111, Lancaster County Gas |
550 MW | Withdrawn / abandoned |
| Tioga County Power Gas ยท ESC Tioga County Power, LLC |
550 MW | Withdrawn / abandoned |
| Gas project AA2-110, Delaware County Gas |
550 MW | Withdrawn / abandoned |
| Allegheny Energy Center LLC Gas |
541 MW | Withdrawn / abandoned |
| Renovo Energy Center Gas ยท Renovo Energy Center, LLC |
504 MW | Withdrawn / abandoned |
| Gas project AB1-108, Lackawanna County Gas |
485 MW | Withdrawn / abandoned |
| Gas project AA2-120, Tioga County Gas |
250 MW | Withdrawn / abandoned |
| Gas project AA2-077, Philadelphia County Gas |
220 MW | Withdrawn / abandoned |
| Gas project AA2-050, Philadelphia County Gas |
210 MW | Withdrawn / abandoned |
| Gas project AB1-111, Lancaster County Gas |
135 MW | Withdrawn / abandoned |
| Gas project AA2-051, Philadelphia County Gas |
130 MW | Withdrawn / abandoned |
| Gas project AA2-078, Philadelphia County Gas |
130 MW | Withdrawn / abandoned |
| Gas project AA2-043, Washington County Gas |
99.0 MW | Withdrawn / abandoned |
| Gas project AB1-110, Lancaster County Gas |
70.0 MW | Withdrawn / abandoned |
| Onshore wind project AA2-069A, Wayne County Onshore wind |
64.6 MW | Withdrawn / abandoned |
| Renovo Energy Center Gas |
41.0 MW | Withdrawn / abandoned |
| Bear Creek Energy Storage Facility Battery storage |
20.0 MW | Withdrawn / abandoned |
| Franklin Generation Facility Gas |
20.0 MW | Withdrawn / abandoned |
| Solar project AB1-126, Franklin County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AB1-074, Philadelphia County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AA2-104, Somerset County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AB1-073, Delaware County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AB1-147, Beaver County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Wilson Battery Storage Battery storage |
20.0 MW | Withdrawn / abandoned |
| Gas project AB1-068, Schuylkill County Gas |
20.0 MW | Withdrawn / abandoned |
| Whitely - Greene Battery Storage Facility Battery storage |
20.0 MW | Withdrawn / abandoned |
| Gas project AB1-179, Tioga County Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-080, Washington County Gas |
19.9 MW | Withdrawn / abandoned |
| Thompson 34.5kV Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-135, Bradford County Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AB1-083, Susquehanna County Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-167, Bradford County Gas |
19.9 MW | Withdrawn / abandoned |
| Niles Valley 34.5kV Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-112, Susquehanna County Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-134, Washington County Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-083, Bradford County Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AA2-166, Lawrence County Gas |
19.9 MW | Withdrawn / abandoned |
| IMG Generation Potter Facility Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AB2-012, Wayne County Gas |
19.9 MW | Withdrawn / abandoned |
| Gas project AB1-084, Susquehanna County Gas |
19.9 MW | Withdrawn / abandoned |
| Solar project AB1-129, Franklin County Solar |
15.0 MW | Withdrawn / abandoned |
| Battery storage project AB1-114, Mercer County Battery storage |
12.5 MW | Withdrawn / abandoned |
| Other project AB1-031, Montgomery County Other |
9.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)