United States โ€บ Grid โ€บ Interconnection queues โ€บ Oregon

OCTARY USA ยท INTERCONNECTION QUEUES

Solar interconnection queue in Oregon

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown578,210 MW
Active in queue8,210 MW57 requests
Agreement signed915 MW11 requests
Withdrawn37718.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

57 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project G0678, Morrow County
Solar
1,200 MWIn study Morrow, ORWest Jun 2021target 2024
Solar project G0687, Sherman County
Solar
900 MWIn study Sherman, ORWest Aug 2021target 2024
Solar project G0669, Crook County
Solar
600 MWIn study Crook, ORWest Feb 2021target 2027
Solar project G0539, Deschutes County
Solar
600 MWAgreement signed Deschutes, ORWest May 2016target 2022
Solar project G0673, Crook County
Solar
600 MWIn study Crook, ORWest Mar 2021target 2028
Solar project G0712, Sherman County
Solar
448 MWIn study Sherman, ORWest Nov 2021target 2025
Solar project G0651, Lake County
Solar
400 MWIn study Lake, ORWest Jul 2020target 2023
Solar project G0866, Sherman County
Solar
300 MWIn study Sherman, ORWest Jun 2023target 2027
Solar project G0711, Sherman County
Solar
300 MWIn study Sherman, ORWest Nov 2021target 2025
Solar project G0944, Morrow County
Solar
261 MWIn study Morrow, ORWest Oct 2023target 2026
Solar project G0367, Wasco County
Solar
202 MWIn study Wasco, ORWest Jun 2009target 2012
Solar project G1002, Sherman County
Solar
200 MWIn study Sherman, ORWest Nov 2023target 2029
Solar project G0655, Lake County
Solar
200 MWIn study Lake, ORWest Aug 2020target 2027
Solar project G0625, Morrow County
Solar
191 MWIn study Morrow, ORWest Jun 2019target 2020
Solar project G0654, Lake County
Solar
170 MWIn study Lake, ORWest Aug 2020target 2027
Solar project 16-058, Jefferson County
Solar
150 MWPaused / redesign Jefferson, ORWest Jul 2016target 2018
Solar project G0527, Lake County
Solar
105 MWIn study Lake, ORWest Feb 2016target 2019
Solar project 734, Crook County
Solar ยท Aurora Solar, LLC
102 MWAgreement signed Crook, ORWest Mar 2016target 2025
Solar project G0368, Wasco County
Solar
101 MWIn study Wasco, ORWest Jun 2009target 2027
Solar project G0532, Morrow County
Solar
100 MWIn study Morrow, ORWest Mar 2016target 2017
Solar project G0706, Morrow County
Solar
100 MWIn study Morrow, ORWest Oct 2021target 2024
Solar project G0713, Morrow County
Solar
100 MWIn study Morrow, ORWest Nov 2021target 2026
Solar project G0879, Lane County
Solar
80.0 MWIn study Lane, ORWest Jun 2023target 2029
Solar project C2-06, Crook County
Solar ยท Gadget Solar LLC
80.0 MWAgreement signed Crook, ORWest Apr 2022target 2036
Solar project PIS101, Crook County
Solar
80.0 MWIn study Crook, ORWest Nov 2025target 2026
Solar project G0517, Morrow County
Solar
76.0 MWIn study Morrow, ORWest Nov 2015target 2018
Solar project 16-060, Jefferson County
Solar
67.0 MWPaused / redesign Jefferson, ORWest Sep 2016target 2018
Solar project QF17-068, Jefferson County
Solar
65.0 MWPaused / redesign Jefferson, ORWest Oct 2017target 2019
Solar project QF19-081, Jefferson County
Solar
53.0 MWAgreement signed Jefferson, ORWest Nov 2019target 2022
Solar project 443, Crook County
Solar ยท Ponderosa Solar, LLC
34.6 MWAgreement signed Crook, ORWest Oct 2012target 2020
Solar project T2-079, Jefferson County
Solar
25.0 MWIn study Jefferson, ORWest Sep 2025target 2026
Solar project G1069, Harney County
Solar
20.0 MWIn study Harney, ORWest Jul 2024target 2025
Solar project G0516, Sherman County
Solar
20.0 MWIn study Sherman, ORWest Oct 2015target 2016
Solar project G0524, Wasco County
Solar
20.0 MWIn study Wasco, ORWest Jan 2016target 2018
Solar project G0570, Lake County
Solar
20.0 MWIn study Lake, ORWest Jul 2017target 2019
Solar project G0571, Lake County
Solar
20.0 MWIn study Lake, ORWest Jul 2017target 2019
Solar project TCS-52, Crook County
Solar ยท Get Along Solar II LLC
20.0 MWAgreement signed Crook, ORWest Apr 2020target 2026
Solar project G0537, Harney County
Solar
20.0 MWIn study Harney, ORWest May 2016target 2019
Solar project TCS-53, Crook County
Solar ยท Get Along Solar XI LLC
20.0 MWAgreement signed Crook, ORWest Apr 2020target 2026
Solar project G0572, Lake County
Solar
20.0 MWIn study Lake, ORWest Jul 2017target 2019
Solar project G0513, Morrow County
Solar
20.0 MWIn study Morrow, ORWest Sep 2015target 2016
Solar project C3-097, Jefferson County
Solar ยท PacifiCorp
19.9 MWIn study Jefferson, ORWest May 2023target 2028
Solar project C3-081, Jefferson County
Solar ยท PacifiCorp
19.9 MWIn study Jefferson, ORWest May 2023target 2028
Solar project PIS099, Jefferson County
Solar ยท PacifiCorp
19.9 MWIn study Jefferson, ORWest Nov 2024target 2027
Solar project PIS095, Jefferson County
Solar ยท PacifiCorp
19.9 MWIn study Jefferson, ORWest Nov 2024target 2027
Solar project G0722, Harney County
Solar
15.0 MWIn study Harney, ORWest Jan 2022target 2024
Solar project G0523, Wasco County
Solar
13.0 MWIn study Wasco, ORWest Jan 2016target 2018
Solar project 752, Malheur County
Solar ยท Fry Foods Inc.
4.2 MWAgreement signed Malheur, ORWest Aug 2024target 2025
Solar project C3-148, Crook County
Solar ยท CP Prineville, LLC
3.0 MWIn study Crook, ORWest May 2023target 2033
Solar project G1075, Lane County
Solar
1.1 MWIn study Lane, ORWest Mar 2025target 2025
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)