Interconnection queue in Oklahoma (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown71,255 MW
Active in queue1,255 MW7 requests
Agreement signed402 MW3 requests
Withdrawn102,048 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

7 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2020-087, Comanche County
Solar
500 MWIn study Comanche, OKSPP Apr 2020target 2026
Solar + storage project GEN-2020-020, Mccurtain County
Solar + storage
202 MWAgreement signed Mccurtain, OKSPP Apr 2020target 2027
Solar + storage project GEN-2020-010, Woodward County
Solar + storage
140 MWIn study Woodward, OKSPP Apr 2020target 2027
Solar + storage project GEN-2020-012, Jackson County
Solar + storage
113 MWIn study Jackson, OKSPP Apr 2020target 2027
Solar project GEN-2020-092, Mayes County
Solar
100 MWIn study Mayes, OKSPP Apr 2020target 2026
Battery storage project GEN-2021-001, Bryan County
Battery storage
100 MWAgreement signed Bryan, OKSPP Dec 2020target 2029
Battery storage project GEN-2020-SR2, Johnston County
Battery storage
100 MWAgreement signed Johnston, OKSPP Aug 2020target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)