Onshore wind project GEN-2017-137, Oklahoma County Onshore wind |
295 MW | Agreement signed |
Oklahoma, OK | SPP |
Nov 2017 | target 2030 |
Onshore wind project GEN-2017-149, Johnston County Onshore wind |
258 MW | Agreement signed |
Johnston, OK | SPP |
Nov 2017 | target 2027 |
Solar project GEN-2017-150, Grady County Solar |
250 MW | Agreement signed |
Grady, OK | SPP |
Nov 2017 | target 2026 |
Solar project GEN-2017-164, Garfield County Solar |
250 MW | Agreement signed |
Garfield, OK | SPP |
Nov 2017 | 2025 |
Onshore wind project GEN-2017-134, Oklahoma County Onshore wind |
250 MW | Agreement signed |
Oklahoma, OK | SPP |
Nov 2017 | target 2030 |
Solar project GEN-2017-141, Wagoner County Solar |
242 MW | Agreement signed |
Wagoner, OK | SPP |
Nov 2017 | target 2027 |
Onshore wind project GEN-2017-233, Grady County Onshore wind |
215 MW | Agreement signed |
Grady, OK | SPP |
Nov 2017 | target 2027 |
Solar project GEN-2017-075, Johnston County Solar |
200 MW | Agreement signed |
Johnston, OK | SPP |
May 2017 | target 2026 |
Onshore wind project GEN-2017-133, Oklahoma County Onshore wind |
200 MW | Agreement signed |
Oklahoma, OK | SPP |
Nov 2017 | target 2030 |
Solar project GEN-2017-092, Muskogee County Solar |
200 MW | Agreement signed |
Muskogee, OK | SPP |
May 2017 | target 2026 |
Solar project GEN-2017-140, Wagoner County Solar |
160 MW | Agreement signed |
Wagoner, OK | SPP |
Nov 2017 | target 2027 |
Solar project GEN-2017-011, Ellis County Solar |
152 MW | Agreement signed |
Ellis, OK | SPP |
May 2017 | target 2026 |
Solar project GEN-2017-171, Comanche County Solar |
150 MW | Agreement signed |
Comanche, OK | SPP |
Nov 2017 | target 2027 |
Solar project GEN-2017-077, Mayes County Solar |
125 MW | Agreement signed |
Mayes, OK | SPP |
May 2017 | 2025 |
Solar project GEN-2017-071, Payne County Solar |
125 MW | Agreement signed |
Payne, OK | SPP |
May 2017 | 2025 |
Solar project GEN-2017-100, Texas County Solar |
103 MW | Agreement signed |
Texas, OK | SPP |
May 2017 | 2025 |
Solar project GEN-2017-061, Mayes County Solar |
102 MW | Agreement signed |
Mayes, OK | SPP |
May 2017 | 2025 |
Solar project GEN-2017-023, Choctaw County Solar |
85.0 MW | Agreement signed |
Choctaw, OK | SPP |
May 2017 | target 2026 |
Solar project GEN-2017-230, Lincoln County Solar |
72.5 MW | Agreement signed |
Lincoln, OK | SPP |
Nov 2017 | target 2027 |
Solar project GEN-2017-074, Mayes County Solar |
72.5 MW | Agreement signed |
Mayes, OK | SPP |
May 2017 | 2025 |
Solar project GEN-2017-073, Mayes County Solar |
72.5 MW | Agreement signed |
Mayes, OK | SPP |
May 2017 | 2025 |
Solar project GEN-2017-072, Payne County Solar |
52.2 MW | Agreement signed |
Payne, OK | SPP |
May 2017 | 2025 |
Solar project GEN-2017-232, Bryan County Solar |
52.2 MW | Agreement signed |
Bryan, OK | SPP |
Nov 2017 | target 2026 |
Battery storage project GEN-2017-178, Garfield County Battery storage |
52.0 MW | Agreement signed |
Garfield, OK | SPP |
Nov 2017 | 2025 |
Solar project GEN-2017-173, Comanche County Solar |
50.0 MW | Agreement signed |
Comanche, OK | SPP |
Nov 2017 | target 2027 |
Solar project GEN-2017-172, Comanche County Solar |
50.0 MW | Agreement signed |
Comanche, OK | SPP |
Nov 2017 | target 2027 |
Battery storage project GEN-2017-117, Canadian County Battery storage |
19.8 MW | Paused / redesign |
Canadian, OK | SPP |
Nov 2017 | target 2029 |