United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Gas interconnection queue in Oklahoma

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3115.1 GW
Active in queue15.1 GW31 requests
Agreement signed2,300 MW8 requests
Withdrawn4018.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

31 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-340, Creek County
Gas
1,400 MWIn study Creek, OKSPP Mar 2025target 2032
Gas project GEN-2024-132, Johnston County
Gas
1,300 MWIn study Johnston, OKSPP Mar 2025target 2031
Gas project GEN-2024-341, Pittsburg County
Gas
1,045 MWIn study Pittsburg, OKSPP Mar 2025target 2031
Gas project ERAS-2025-004, Oklahoma County
Gas
763 MWIn study Oklahoma, OKSPP Sep 2025target 2030
Gas project ERAS-2025-026, Comanche County
Gas
744 MWIn study Comanche, OKSPP Oct 2025target 2029
Gas project GEN-2024-299, Oklahoma County
Gas
744 MWIn study Oklahoma, OKSPP Mar 2025target 2032
Gas project ERAS-2025-024, Comanche County
Gas
744 MWIn study Comanche, OKSPP Oct 2025target 2029
Gas project GEN-2024-128, Caddo County
Gas
690 MWIn study Caddo, OKSPP Mar 2025target 2030
Gas project GEN-2024-GR5, Chouteau County
Gas
594 MWAgreement signed Chouteau, OKSPP Aug 2024target 2026
Gas project ERAS-2025-023, Rogers County
Gas
510 MWIn study Rogers, OKSPP Oct 2025target 2029
Gas project ERAS-2025-010, Oklahoma County
Gas
496 MWIn study Oklahoma, OKSPP Sep 2025target 2029
Gas project GEN-2024-013, Mcclain County
Gas
496 MWIn study Mcclain, OKSPP Aug 2024target 2030
Gas project GEN-2024-321, Seminole County
Gas
493 MWIn study Seminole, OKSPP Mar 2025target 2030
Gas project GEN-2024-GR1, Oklahoma County
Gas
492 MWAgreement signed Oklahoma, OKSPP Jan 2024target 2026
Gas project GI-129, Payne County
Gas
460 MWIn study Payne, OKSoutheast Jul 2025target 2030
Gas project GI-104, Payne County
Gas
460 MWAgreement signed Payne, OKSoutheast Jul 2022target 2026
Gas project GI-130, Payne County
Gas
460 MWIn study Payne, OKSoutheast Jul 2025target 2030
Gas project GI-103, Creek County
Gas
460 MWAgreement signed Creek, OKSoutheast Jul 2022target 2027
Gas project GEN-2024-247, Payne County
Gas
457 MWIn study Payne, OKSPP Mar 2025target 2030
Gas project GEN-2024-323, Choctaw County
Gas
357 MWIn study Choctaw, OKSPP Mar 2025target 2029
Gas project GEN-2024-254, Canadian County
Gas
300 MWIn study Canadian, OKSPP Mar 2025target 2027
Gas project GEN-2024-255, Oklahoma County
Gas
300 MWIn study Oklahoma, OKSPP Mar 2025target 2027
Gas project GEN-2024-252, Canadian County
Gas
300 MWIn study Canadian, OKSPP Mar 2025target 2027
Gas project GEN-2024-293, Oklahoma County
Gas
248 MWIn study Oklahoma, OKSPP Mar 2025target 2033
Gas project ERAS-2025-003, Oklahoma County
Gas
186 MWIn study Oklahoma, OKSPP Sep 20252025
Gas project GEN-2024-286, Le Flore County
Gas
136 MWIn study Le Flore, OKSPP Mar 2025target 2031
Gas project GEN-2024-334, Kay County
Gas
124 MWIn study Kay, OKSPP Mar 2025target 2029
Gas project GEN-2023-GR1, Caddo County
Gas
97.5 MWAgreement signed Caddo, OKSPP Jan 20232025
Gas project GEN-2023-GR2, Oklahoma County
Gas
94.2 MWAgreement signed Oklahoma, OKSPP Feb 2023target 2026
Gas project GI-78, Mayes County
Gas
52.0 MWAgreement signed Mayes, OKSoutheast Jan 2019target 2020
Gas project GI-77, Mayes County
Gas
50.0 MWAgreement signed Mayes, OKSoutheast Jan 2019target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)