United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Ohio (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown253,684 MW
Active in queue3,684 MW25 requests
Agreement signed0.0 MW0 requests
Withdrawn192,807 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

25 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project AH1-680, Carroll County
Gas Β· Chestnut Run Energy LLC
1,300 MWIn study Carroll, OHPJM Apr 2025
Gas project AH1-711, Wood County
Gas Β· Troy Energy, LLC
408 MWIn study Wood, OHPJM Apr 2025
Solar project AH1-055, Jackson County
Solar Β· Furnace Solar, LLC
220 MWIn study Jackson, OHPJM Feb 2025target 2026
Solar project AH1-580, Harrison County
Solar Β· Energy Pastures Solar Project, LLC
200 MWIn study Harrison, OHPJM Mar 2025target 2025
Solar project AG2-104, Madison County
Solar Β· Oak Run Solar Project, LLC
200 MWIn study Madison, OHPJM Mar 2025target 2025
Battery storage project AG2-329, Wyandot County
Battery storage Β· Wombat Solar LLC
200 MWIn study Wyandot, OHPJM Mar 2025target 2024
Solar project AG2-082, Harrison County
Solar Β· Energy Pastures Solar Project, LLC
200 MWIn study Harrison, OHPJM Mar 2025target 2024
Solar project AH1-537, Highland County
Solar Β· Riverlake Energy, LLC
179 MWIn study Highland, OHPJM Mar 2025target 2025
Green Camp Solar II
Solar + storage Β· Riverlake Energy, LLC
110 MWIn study Marion, OHPJM Feb 2025target 2025
Solar + storage project AG2-548, Jackson County
Solar + storage Β· Hamden Energy LLC
80.0 MWIn study Jackson, OHPJM Feb 2025target 2023
Solar + storage project AG2-665, Jackson County
Solar + storage Β· Hamden Energy LLC
80.0 MWIn study Jackson, OHPJM Feb 2025target 2024
Solar project AG2-119, Marion County
Solar Β· Marion County Solar Project II, LLC
80.0 MWIn study Marion, OHPJM Feb 2025target 2024
Gas project AH1-699, Columbiana County
Gas Β· South Field Energy LLC
69.0 MWIn study Columbiana, OHPJM Apr 2025
Battery storage project AG2-289, Seneca County
Battery storage Β· Chinchilla Solar LLC
66.6 MWIn study Seneca, OHPJM Feb 2025target 2024
Solar project AH1-282, Morrow County
Solar Β· Woodbury Solar, LLC
49.9 MWIn study Morrow, OHPJM Mar 2025target 2025
Solar project AG2-109, Huron County
Solar Β· Rosemary Solar, LLC
40.0 MWIn study Huron, OHPJM Feb 2025target 2023
Battery storage project AG2-290, Seneca County
Battery storage Β· Chinchilla Solar LLC
38.4 MWIn study Seneca, OHPJM Feb 2025target 2024
Gas project AH1-706, Trumbull County
Gas Β· Clean Energy Future - Lordstown, LLC
30.5 MWIn study Trumbull, OHPJM Apr 2025
Gas project AH1-719, Washington County
Gas Β· Washington Power Generation LLC
24.0 MWIn study Washington, OHPJM Apr 2025
Gas project AH1-686, Lawrence County
Gas Β· Hanging Rock Power Company LLC
24.0 MWIn study Lawrence, OHPJM Apr 2025
Gas project AH1-704, Monroe County
Gas Β· Long Ridge Energy Generation LLC
24.0 MWIn study Monroe, OHPJM Apr 2025
Solar project AH1-059, Knox County
Solar Β· Frasier Solar, LLC
21.0 MWIn study Knox, OHPJM Mar 2025target 2024
Crossroads Solar I
Solar Β· Crossroads Solar I, LLC
20.0 MWIn study Morrow, OHPJM Apr 2025target 2024
Other project AH1-661, Muskingum County
Other Β· Tallgrass Muskingum Community Power, LLC
10.1 MWIn study Muskingum, OHPJM Feb 2025target 2023
Solar project AG2-057, Morrow County
Solar Β· Crossroads Solar I, LLC
10.0 MWIn study Morrow, OHPJM Apr 2025target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)