United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in North Dakota (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown214,792 MW
Active in queue1,820 MW9 requests
Agreement signed170 MW1 requests
Withdrawn214,792 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

21 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J2606, Steele County
Battery storage
361 MWWithdrawn / abandoned Steele, NDMISO Sep 2022target 2027
Solar + storage project J2883, Mercer County
Solar + storage
347 MWWithdrawn / abandoned Mercer, NDMISO Sep 2022target 2027
Solar + storage project J2665, Mercer County
Solar + storage
347 MWWithdrawn / abandoned Mercer, NDMISO Sep 2022target 2027
Solar + storage project J2912, Mercer County
Solar + storage
347 MWWithdrawn / abandoned Mercer, NDMISO Sep 2022target 2027
Onshore wind project J2605, Steele County
Onshore wind
339 MWWithdrawn / abandoned Steele, NDMISO Sep 2022target 2027
Onshore wind project J2327, Lamoure County
Onshore wind
300 MWWithdrawn / abandoned Lamoure, NDMISO Sep 2022target 2026
Onshore wind project J2367, Lamoure County
Onshore wind
250 MWWithdrawn / abandoned Lamoure, NDMISO Sep 2022target 2030
Onshore wind project J2368, Lamoure County
Onshore wind
250 MWWithdrawn / abandoned Lamoure, NDMISO Sep 2022target 2030
Onshore wind project J2344, Stutsman County
Onshore wind
200 MWWithdrawn / abandoned Stutsman, NDMISO Sep 2022target 2026
Solar + storage project J3182, Oliver County
Solar + storage
200 MWWithdrawn / abandoned Oliver, NDMISO Sep 2022target 2027
Solar + storage project J2772, Mercer County
Solar + storage
200 MWWithdrawn / abandoned Mercer, NDMISO Sep 2022target 2027
Battery storage project GEN-2022-245, Kidder County
Battery storage
200 MWWithdrawn / abandoned Kidder, NDSPP Mar 2022target 2028
Solar project J1852, Cass County
Solar
200 MWWithdrawn / abandoned Cass, NDMISO Jun 2022target 2025
Battery storage project J2518, Lamoure County
Battery storage
200 MWWithdrawn / abandoned Lamoure, NDMISO Sep 2022target 2024
Solar project GEN-2022-018, Dunn County
Solar
186 MWWithdrawn / abandoned Dunn, NDSPP Jun 20222025
Onshore wind project GEN-2022-037, Williams County
Onshore wind
181 MWWithdrawn / abandoned Williams, NDSPP Jun 20222025
Solar project GEN-2022-078, Bowman County
Solar
180 MWWithdrawn / abandoned Bowman, NDSPP Sep 2022target 2028
Onshore wind project J1888, Oliver County
Onshore wind
175 MWWithdrawn / abandoned Oliver, NDMISO Jan 2022target 2024
Onshore wind project J3091, Logan County
Onshore wind
145 MWWithdrawn / abandoned Logan, NDMISO Sep 2022target 2026
Battery storage project GEN-2022-SR1, Burke County
Battery storage
104 MWWithdrawn / abandoned Burke, NDSPP Mar 2022target 2022
Battery storage project J2896, Sargent County
Battery storage
80.0 MWWithdrawn / abandoned Sargent, NDMISO Sep 2022target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)