United States β€Ί Grid β€Ί Interconnection queues β€Ί Nevada

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Nevada (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown135,632 MW
Active in queue5,632 MW13 requests
Agreement signed2,642 MW9 requests
Withdrawn286,600 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Arida 2 Solar Farm
Solar + storage
1,400 MWIn study Clark, NVCAISO Apr 2019target 2029
Other project Company KD, White Pine County
Other
750 MWPaused / redesign White Pine, NVWest Sep 2019target 2026
Bonanza Peak Solar Farm
Solar + storage
641 MWAgreement signed Clark, NVCAISO Apr 2019target 2027
Bonanza Solar
Solar + storage
600 MWAgreement signed Clark, NVCAISO Apr 2019target 2028
Yellow Pine 3
Solar + storage
517 MWAgreement signed Clark, NVCAISO Apr 2019target 2026
Solar + storage project Q67, Clark County
Solar + storage
500 MWIn study Clark, NVWest Mar 2019target 2022
Rough Hat Hybrid Solar
Solar + storage
404 MWAgreement signed Nye, NVCAISO Apr 2019target 2028
Solar + storage project Company JX, Pershing County
Solar + storage
340 MWPaused / redesign Pershing, NVWest Sep 2019target 2023
Solar + storage project Company 181, Clark County
Solar + storage
200 MWAgreement signed Clark, NVWest Sep 2019target 2028
Solar + storage project Company 174, Clark County
Solar + storage
100 MWAgreement signed Clark, NVWest Mar 2019target 2023
Battery storage project Company JW, Washoe County
Battery storage
100 MWAgreement signed Washoe, NVWest Sep 2019target 2027
Battery storage project Company JV, Carson City County
Battery storage
50.0 MWAgreement signed Carson City, NVWest Mar 2019target 2023
Battery storage project Company 185, Clark County
Battery storage
30.0 MWAgreement signed Clark, NVWest Sep 2019target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)