Withdrawn queue requests in Nebraska (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown111,840 MW
Active in queue1,690 MW9 requests
Agreement signed1,380 MW8 requests
Withdrawn111,840 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2017-212, Cedar County
Solar
310 MWWithdrawn / abandoned Cedar, NESPP Nov 2017target 2021
Solar project GEN-2017-008, Nuckolls County
Solar
305 MWWithdrawn / abandoned Nuckolls, NESPP Apr 2017target 2019
Onshore wind project GEN-2017-165, Holt County
Onshore wind
288 MWWithdrawn / abandoned Holt, NESPP Nov 2017target 2020
Onshore wind project GEN-2017-138, Holt County
Onshore wind
252 MWWithdrawn / abandoned Holt, NESPP Nov 2017target 2020
Onshore wind project GEN-2017-139, Holt County
Onshore wind
252 MWWithdrawn / abandoned Holt, NESPP Nov 2017target 2020
Solar project GEN-2017-055, Lancaster County
Solar
228 MWWithdrawn / abandoned Lancaster, NESPP May 20172023
Onshore wind project GEN-2017-031, Garden County
Onshore wind
100 MWWithdrawn / abandoned Garden, NESPP May 2017target 2021
Onshore wind project GEN-2017-006, Fillmore County
Onshore wind
73.6 MWWithdrawn / abandoned Fillmore, NESPP Apr 2017target 2022
Solar project GEN-2017-037, Scotts Bluff County
Solar
20.0 MWWithdrawn / abandoned Scotts Bluff, NESPP May 2017target 2018
Onshore wind project GEN-2017-241, Dawson County
Onshore wind
10.0 MWWithdrawn / abandoned Dawson, NESPP Jul 2017target 2018
Onshore wind project GEN-2017-085, Saline County
Onshore wind
0.6 MWWithdrawn / abandoned Saline, NESPP May 20172023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)