United States β€Ί Grid β€Ί Interconnection queues β€Ί Nebraska

ONSHORE WIND Β· SPP

Onshore wind project GEN-2017-006, Fillmore County

Onshore wind project GEN-2017-006, Fillmore County is a 73.6 MW onshore wind request withdrawn in the SPP interconnection queue, in Fillmore County, Nebraska, connecting to NPPD.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2017 (completed)
  2. Withdrawn / abandonedNov 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-006
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Tobias 345kV Substation
Location
Fillmore County, Nebraska
Technology
Wind: 73.6 MW
Total requested
73.6 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
14 April 2017
Proposed online date
October 2022
Withdrawn
November 2020

Location

Marker shows the centre of Fillmore County; the queue data does not give exact sites.

Power plants in Nebraska Β· Transmission lines in Nebraska

Other requests in Fillmore County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem