United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Montana (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown82,125 MW
Active in queue4,311 MW11 requests
Agreement signed1,010 MW3 requests
Withdrawn82,125 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

8 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 1115, Wheatland County
Onshore wind
600 MWWithdrawn / abandoned Wheatland, MTWest Feb 2019target 2021
Wind + storage project 369, Rosebud County
Wind + storage
500 MWWithdrawn / abandoned Rosebud, MTWest Nov 2019target 2024
Solar project G0630, Deer Lodge County
Solar
300 MWWithdrawn / abandoned Deer Lodge, MTWest Oct 2019target 2022
Solar + storage project 368, Beaverhead County
Solar + storage
200 MWWithdrawn / abandoned Beaverhead, MTWest Oct 2019target 2021
Gas project 370, Yellowstone County
Gas
175 MWWithdrawn / abandoned Yellowstone, MTWest Nov 2019target 2023
Solar + storage project 365, Silver Bow County
Solar + storage
150 MWWithdrawn / abandoned Silver Bow, MTWest Aug 2019target 2020
Solar project GEN-2019-043, Fallon County
Solar
150 MWWithdrawn / abandoned Fallon, MTSPP May 20192023
Battery storage project GEN-2019-024, Wibaux County
Battery storage
50.0 MWWithdrawn / abandoned Wibaux, MTSPP May 2019target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)