United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Mississippi (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown111,489 MW
Active in queue1,489 MW11 requests
Agreement signed0.0 MW0 requests
Withdrawn489,822 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

11 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J3623, Sunflower County
Onshore wind
350 MWIn study Sunflower, MSMISO Apr 2024target 2028
Solar + storage project J3764, Madison County
Solar + storage
170 MWIn study Madison, MSMISO Apr 2024target 2028
Solar project J3987, Amite County
Solar
165 MWIn study Amite, MSMISO Oct 2024target 2030
Onshore wind project J3900, Sunflower County
Onshore wind
163 MWIn study Sunflower, MSMISO Dec 2024target 2030
Solar project J3913, Amite County
Solar
140 MWIn study Amite, MSMISO Oct 2024target 2030
Solar project 672, Rankin County
Solar
140 MWIn study Rankin, MSSoutheast Oct 2024target 2027
Solar project IC-1244, Newton County
Solar
100 MWPaused / redesign Newton, MSSoutheast Mar 2024target 2029
Solar project J3590, Humphreys County
Solar
75.0 MWIn study Humphreys, MSMISO Apr 2024target 2028
Solar + storage project 671, Monroe County
Solar + storage
75.0 MWIn study Monroe, MSSoutheast Oct 2024target 2029
Onshore wind project J3592, Sunflower County
Onshore wind
57.0 MWIn study Sunflower, MSMISO Apr 2024target 2028
Gas project 656, Benton County
Gas
54.0 MWIn study Benton, MSSoutheast Oct 2024target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)