Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown142,108 MW
Active in queue2,108 MW14 requests
Agreement signed305 MW4 requests
Withdrawn425,320 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J2302, St. Helena Parish County
Solar + storage
400 MWIn study St. Helena Parish, LAMISO Nov 2021target 2027
Solar project J2317, Ouachita Parish County
Solar
225 MWIn study Ouachita Parish, LAMISO Dec 2021target 2027
Solar project J1870, Tangipahoa Parish County
Solar
200 MWIn study Tangipahoa Parish, LAMISO Aug 2021target 2028
Solar project J2224, Iberville Parish County
Solar
200 MWIn study Iberville Parish, LAMISO Aug 2021target 2025
Solar project J2228, Concordia Parish County
Solar
200 MWIn study Concordia Parish, LAMISO Dec 2021target 2027
Solar project J1851, Morehouse Parish County
Solar
185 MWIn study Morehouse Parish, LAMISO Nov 2021target 2026
Solar project J2249, Acadia Parish County
Solar
144 MWIn study Acadia Parish, LAMISO Dec 2021target 2027
Gas project J1833, Lafourche Parish County
Gas
115 MWAgreement signed Lafourche Parish, LAMISO Oct 2021target 2025
Solar project J1904, Acadia Parish County
Solar
100 MWIn study Acadia Parish, LAMISO Aug 2021target 2028
Solar project J2208, De Soto Parish County
Solar
99.0 MWIn study De Soto Parish, LAMISO Aug 2021target 2024
Solar project J1827, Morehouse Parish County
Solar
90.0 MWAgreement signed Morehouse Parish, LAMISO Oct 2021target 2026
Solar project J1561, Acadia Parish County
Solar
75.0 MWAgreement signed Acadia Parish, LAMISO Oct 2021target 2026
Solar project J2292, Calcasieu Parish County
Solar
50.0 MWIn study Calcasieu Parish, LAMISO Sep 2021target 2027
Battery storage project J1602, Ouachita Parish County
Battery storage
25.0 MWAgreement signed Ouachita Parish, LAMISO Nov 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)