United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Kentucky (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown133,049 MW
Active in queue2,234 MW9 requests
Agreement signed169 MW2 requests
Withdrawn133,049 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 629, Todd County
Gas
1,224 MWWithdrawn / abandoned Todd, KYSoutheast Jun 2024
Onshore wind project LGE-GIS-2024-007, Harlan County
Onshore wind
250 MWWithdrawn / abandoned Harlan, KYSoutheast Jun 2024target 2028
Battery storage project J3559, Hancock County
Battery storage
250 MWWithdrawn / abandoned Hancock, KYMISO Apr 2024target 2027
Battery storage project J3726, Hancock County
Battery storage
200 MWWithdrawn / abandoned Hancock, KYMISO Mar 2024target 2027
Battery storage project J3490, Caldwell County
Battery storage
200 MWWithdrawn / abandoned Caldwell, KYMISO Mar 2024target 2027
Solar + storage project LGE-GIS-2024-005, Breckinridge County
Solar + storage
200 MWWithdrawn / abandoned Breckinridge, KYSoutheast May 2024target 2027
Solar project J3393, Henderson County
Solar
150 MWWithdrawn / abandoned Henderson, KYMISO Apr 2024target 2027
Solar project J3245, Breckinridge County
Solar
150 MWWithdrawn / abandoned Breckinridge, KYMISO Mar 2024target 2028
Solar project LGE-GIS-2024-008, Crittenden County
Solar
150 MWWithdrawn / abandoned Crittenden, KYSoutheast Jun 2024target 2027
Onshore wind project J3779, Henderson County
Onshore wind
100 MWWithdrawn / abandoned Henderson, KYMISO Apr 2024target 2026
Solar + storage project LGE-GIS-2024-001, Grayson County
Solar + storage
75.0 MWWithdrawn / abandoned Grayson, KYSoutheast Jan 2024target 2027
Solar + storage project J3794, Daviess County
Solar + storage
50.0 MWWithdrawn / abandoned Daviess, KYMISO Apr 2024target 2028
Solar project LGE-GIS-2024-003, Croydon County
Solar
50.0 MWWithdrawn / abandoned Croydon, KYSoutheast Mar 2024target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)