United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Kansas (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown163,534 MW
Active in queue3,534 MW16 requests
Agreement signed3,534 MW16 requests
Withdrawn447,630 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2017-195, Johnson County
Solar
500 MWAgreement signed Johnson, KSSPP Nov 2017target 2030
Onshore wind project GEN-2017-183, Hodgeman County
Onshore wind
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Solar project GEN-2017-184, Hodgeman County
Solar
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Onshore wind project GEN-2017-120, Dickinson County
Onshore wind
260 MWAgreement signed Dickinson, KSSPP Nov 2017target 2028
Onshore wind project GEN-2017-004, Cloud County
Onshore wind
202 MWAgreement signed Cloud, KSSPP Apr 2017target 2027
Solar project GEN-2017-226, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Battery storage project GEN-2017-227, Sedgwick County
Battery storage
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Solar project GEN-2017-220, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2026
Onshore wind project GEN-2017-121, Sumner County
Onshore wind
200 MWAgreement signed Sumner, KSSPP Nov 2017target 2026
Solar project GEN-2017-018, Barber County
Solar
189 MWAgreement signed Barber, KSSPP May 20172025
Onshore wind project GEN-2017-119, Cloud County
Onshore wind
180 MWAgreement signed Cloud, KSSPP Nov 2017target 2027
Battery storage project GEN-2017-221, Sedgwick County
Battery storage
152 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2026
Onshore wind project GEN-2017-086, Harper County
Onshore wind
150 MWAgreement signed Harper, KSSPP May 20172025
Battery storage project GEN-2017-196, Johnson County
Battery storage
128 MWAgreement signed Johnson, KSSPP Nov 2017target 2030
Solar project GEN-2017-068, Sumner County
Solar
104 MWAgreement signed Sumner, KSSPP May 2017target 2028
Solar project GEN-2017-022, Wilson County
Solar
65.0 MWAgreement signed Wilson, KSSPP May 2017target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)