πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Kansas (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown133,678 MW
Active in queue1,658 MW9 requests
Agreement signed0.0 MW0 requests
Withdrawn133,678 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2022-086, Finney County
Solar
700 MWWithdrawn / abandoned Finney, KSSPP Nov 2022target 2027
Solar project GEN-2022-076, Stevens County
Solar
500 MWWithdrawn / abandoned Stevens, KSSPP Sep 2022target 2026
Onshore wind project GEN-2022-059, Stevens County
Onshore wind
500 MWWithdrawn / abandoned Stevens, KSSPP Jun 20222025
Onshore wind project GEN-2022-095, Osborne County
Onshore wind
250 MWWithdrawn / abandoned Osborne, KSSPP Nov 2022target 2028
Onshore wind project GEN-2022-094, Osborne County
Onshore wind
250 MWWithdrawn / abandoned Osborne, KSSPP Nov 2022target 2028
Onshore wind project GEN-2022-096, Osborne County
Onshore wind
225 MWWithdrawn / abandoned Osborne, KSSPP Nov 2022target 2028
Battery storage project GEN-2022-081, Washington County
Battery storage
218 MWWithdrawn / abandoned Washington, KSSPP Sep 2022target 2027
Solar project GEN-2022-025, Decatur County
Solar
200 MWWithdrawn / abandoned Decatur, KSSPP Jun 20222025
Solar project GEN-2022-062, Bourbon County
Solar
200 MWWithdrawn / abandoned Bourbon, KSSPP Jul 20222025
Solar project GEN-2022-005, Labette County
Solar
200 MWWithdrawn / abandoned Labette, KSSPP May 2022target 2028
Solar project GEN-2022-026, Decatur County
Solar
200 MWWithdrawn / abandoned Decatur, KSSPP Jun 20222025
Solar project GEN-2022-002, Finney County
Solar
135 MWWithdrawn / abandoned Finney, KSSPP May 2022target 2026
Solar project GEN-2022-041, Cowley County
Solar
100 MWWithdrawn / abandoned Cowley, KSSPP Jun 20222025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)