Solar project GEN-2022-062, Bourbon County

Solar project GEN-2022-062, Bourbon County is a 200 MW solar request withdrawn in the SPP interconnection queue, in Bourbon County, Kansas, connecting to NEET.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2022 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-062
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NEET
Connection point (POI)
Wolf Creek- Blackberry 345 kV
Location
Bourbon County, Kansas
Technology
Solar: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
8 July 2022
Proposed online date
December 2025
Came online
December 2025
Withdrawn
March 2025

Location

Marker shows the centre of Bourbon County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Bourbon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem