United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

SOLAR Β· SPP

Solar project GEN-2022-005, Labette County

Solar project GEN-2022-005, Labette County is a 200 MW solar request withdrawn in the SPP interconnection queue, in Labette County, Kansas, connecting to WERE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2022 (completed)
  2. Withdrawn / abandonedSep 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-005
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Northeast Parsons 138kV Substation
Location
Labette County, Kansas
Technology
Solar: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
25 May 2022
Proposed online date
December 2028
Withdrawn
September 2025

Location

Marker shows the centre of Labette County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Labette County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem