Withdrawn queue requests in Kansas (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown101,245 MW
Active in queue4,490 MW18 requests
Agreement signed1,307 MW6 requests
Withdrawn101,245 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

10 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2021-045, Sherman County
Onshore wind
300 MWWithdrawn / abandoned Sherman, KSSPP Apr 2021target 2026
Solar + storage project GEN-2021-084, Kearny County
Solar + storage
180 MWWithdrawn / abandoned Kearny, KSSPP Apr 2021target 2028
Solar + storage project GEN-2021-078, Finney County
Solar + storage
160 MWWithdrawn / abandoned Finney, KSSPP Apr 2021target 2028
Solar project GEN-2021-061, Sedgwick County
Solar
100 MWWithdrawn / abandoned Sedgwick, KSSPP Apr 20212025
Solar + storage project GEN-2021-087, Seward County
Solar + storage
100 MWWithdrawn / abandoned Seward, KSSPP Apr 2021target 2028
Solar + storage project GEN-2021-085, Ford County
Solar + storage
100 MWWithdrawn / abandoned Ford, KSSPP Apr 2021target 2027
Battery storage project GEN-2021-102, Douglas County
Battery storage
80.0 MWWithdrawn / abandoned Douglas, KSSPP May 20212025
Onshore wind project GEN-2021-022, Kiowa County
Onshore wind
75.0 MWWithdrawn / abandoned Kiowa, KSSPP Apr 2021target 2026
Battery storage project GEN-2021-013, Lincoln County
Battery storage
74.9 MWWithdrawn / abandoned Lincoln, KSSPP Apr 20212025
Solar project GEN-2021-011, Cloud County
Solar
74.9 MWWithdrawn / abandoned Cloud, KSSPP Apr 20212025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)