Battery storage interconnection queue in Iowa

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown223,290 MW
Active in queue3,290 MW22 requests
Agreement signed100 MW2 requests
Withdrawn182,252 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

22 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J2469, Linn County
Battery storage
300 MWIn study Linn, IAMISO Sep 2022target 2027
Surplus; J449
Battery storage
202 MWIn study Mitchell, IAMISO Mar 2025target 2027
Surplus; J1190
Battery storage
200 MWIn study Clinton, IAMISO Jul 2025target 2026
Battery storage project J3551, Mahaska County
Battery storage
200 MWIn study Mahaska, IAMISO Apr 2024target 2027
Surplus; J416
Battery storage
200 MWIn study Franklin, IAMISO Aug 2025target 2026
Battery storage project J3780, Buchanan County
Battery storage
200 MWIn study Buchanan, IAMISO Apr 2024target 2028
Battery storage project J2545, Buchanan County
Battery storage
200 MWIn study Buchanan, IAMISO Sep 2022target 2026
Battery storage project J4173, Wapello County
Battery storage
199 MWIn study Wapello, IAMISO Oct 2025target 2028
Battery storage project J4155, Linn County
Battery storage
195 MWIn study Linn, IAMISO Oct 2025target 2029
Battery storage project J2653, Polk County
Battery storage
170 MWIn study Polk, IAMISO Sep 2022target 2027
Battery storage project J2655, Polk County
Battery storage
170 MWIn study Polk, IAMISO Sep 2022target 2026
Replacing 150 MW of coal generation with BESS at Lansing; Lansing 4
Battery storage
150 MWIn study Allamakee, IAMISO Apr 2025target 2026
Replacing 130 MW of coal generation with BESS at Lansing; Lansing 4
Battery storage
130 MWIn study Allamakee, IAMISO Apr 2025target 2026
Battery storage project J3159, Dubuque County
Battery storage
100 MWIn study Dubuque, IAMISO Sep 2022target 2027
Battery storage project J2949, Marshall County
Battery storage
100 MWIn study Marshall, IAMISO Sep 2022target 2027
Battery storage project J3158, Cerro Gordo County
Battery storage
100 MWIn study Cerro Gordo, IAMISO Sep 2022target 2027
Battery storage project J2066, Henry County
Battery storage
100 MWIn study Henry, IAMISO Aug 2021target 2022
Battery storage project J2120, Linn County
Battery storage
100 MWIn study Linn, IAMISO Aug 2021target 2025
Battery storage project J4172, Wapello County
Battery storage
99.0 MWIn study Wapello, IAMISO Oct 2025target 2028
Surplus; J495
Battery storage
75.0 MWIn study Kossuth, IAMISO Jul 2025target 2026
Battery storage project J1477, Scott County
Battery storage
50.0 MWAgreement signed Scott, IAMISO Apr 2019target 2024
Battery storage project J1229, Muscatine County
Battery storage
50.0 MWAgreement signed Muscatine, IAMISO Apr 2019target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)