United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Idaho (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown122,109 MW
Active in queue2,109 MW12 requests
Agreement signed200 MW2 requests
Withdrawn549,728 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project G0956, Benewah County
Onshore wind
400 MWIn study Benewah, IDWest Oct 2023target 2026
Solar project 737, Bingham County
Solar
280 MWIn study Bingham, IDWest Sep 2023target 2027
Solar + storage project G0945, Fremont County
Solar + storage
202 MWIn study Fremont, IDWest Oct 2023target 2026
Solar + storage project 710, Ada County
Solar + storage
200 MWIn study Ada, IDWest Mar 2023target 2026
Solar + storage project 725, Bingham County
Solar + storage
175 MWIn study Bingham, IDWest Jun 2023target 2027
Onshore wind project S0022, Bingham County
Onshore wind
152 MWIn study Bingham, IDWest Oct 2023target 2027
Solar + storage project 716, Ada County
Solar + storage
150 MWIn study Ada, IDWest May 2023target 2028
Solar + storage project 708, Ada County
Solar + storage
150 MWIn study Ada, IDWest Mar 2023target 2028
Battery storage project 723, Canyon County
Battery storage
100 MWIn study Canyon, IDWest Jun 2023target 2027
Solar + storage project 719, Blaine County
Solar + storage Β· Moonstone Energy 2, LLC
100 MWAgreement signed Blaine, IDWest Jun 2023target 2028
Battery storage project 724, Canyon County
Battery storage
100 MWIn study Canyon, IDWest Jun 2023target 2027
Solar + storage project 718, Blaine County
Solar + storage Β· Moonstone Energy, LLC
100 MWAgreement signed Blaine, IDWest Jun 2023target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)