United States β€Ί Grid β€Ί Interconnection queues β€Ί Georgia

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Georgia (2013 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown421,184 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn421,184 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

42 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-291, Burke County
Solar
100 MWWithdrawn / abandoned Burke, GASoutheast Apr 2013
Solar project IC-308, Tattnall County
Solar
80.0 MWWithdrawn / abandoned Tattnall, GASoutheast Jul 2013
Solar project IC-326, Clay County
Solar
80.0 MWWithdrawn / abandoned Clay, GASoutheast Nov 2013
Solar project IC-321, Wayne County
Solar
50.0 MWWithdrawn / abandoned Wayne, GASoutheast Oct 2013
Solar project IC-324, Early County
Solar
50.0 MWWithdrawn / abandoned Early, GASoutheast Nov 2013
Solar project IC-322, Wilkinson County
Solar
50.0 MWWithdrawn / abandoned Wilkinson, GASoutheast Oct 2013
Solar project IC-328, Seminole County
Solar
50.0 MWWithdrawn / abandoned Seminole, GASoutheast Dec 2013
Solar project IC-320, Wayne County
Solar
50.0 MWWithdrawn / abandoned Wayne, GASoutheast Oct 2013
Solar project IC-327, Decatur County
Solar
50.0 MWWithdrawn / abandoned Decatur, GASoutheast Dec 2013
Solar project IC-286, Wheeler County
Solar
20.0 MWWithdrawn / abandoned Wheeler, GASoutheast Mar 2013
Solar project IC-293, Dodge County
Solar
20.0 MWWithdrawn / abandoned Dodge, GASoutheast Apr 2013
Solar project IC-307, Pierce County
Solar
20.0 MWWithdrawn / abandoned Pierce, GASoutheast Jul 2013
Solar project IC-304, Macon County
Solar
20.0 MWWithdrawn / abandoned Macon, GASoutheast Jun 2013
Solar project IC-283, Dooly County
Solar
20.0 MWWithdrawn / abandoned Dooly, GASoutheast Mar 2013
Solar project IC-305, Crawford County
Solar
20.0 MWWithdrawn / abandoned Crawford, GASoutheast Jun 2013
Solar project IC-298, Jenkins County
Solar
20.0 MWWithdrawn / abandoned Jenkins, GASoutheast May 2013
Solar project IC-288, Wheeler County
Solar
20.0 MWWithdrawn / abandoned Wheeler, GASoutheast Apr 2013
Solar project IC-280, Echols County
Solar
20.0 MWWithdrawn / abandoned Echols, GASoutheast Feb 2013
Solar project IC-315, Mitchell County
Solar
20.0 MWWithdrawn / abandoned Mitchell, GASoutheast Aug 2013
Solar project IC-303, Lincoln County
Solar
20.0 MWWithdrawn / abandoned Lincoln, GASoutheast Jun 2013
Solar project IC-282, Dooly County
Solar
20.0 MWWithdrawn / abandoned Dooly, GASoutheast Mar 2013
Solar project IC-290, Burke County
Solar
20.0 MWWithdrawn / abandoned Burke, GASoutheast Apr 2013
Solar project IC-314, Calhoun County
Solar
20.0 MWWithdrawn / abandoned Calhoun, GASoutheast Aug 2013
Solar project IC-281, Echols County
Solar
20.0 MWWithdrawn / abandoned Echols, GASoutheast Feb 2013
Solar project IC-292, Laurens County
Solar
20.0 MWWithdrawn / abandoned Laurens, GASoutheast Apr 2013
Solar project IC-302, Bartow County
Solar
20.0 MWWithdrawn / abandoned Bartow, GASoutheast Jun 2013
Solar project IC-300, Clay County
Solar
20.0 MWWithdrawn / abandoned Clay, GASoutheast May 2013
Solar project IC-301, Tattnall County
Solar
20.0 MWWithdrawn / abandoned Tattnall, GASoutheast Jun 2013
Solar project IC-296, Bulloch County
Solar
20.0 MWWithdrawn / abandoned Bulloch, GASoutheast May 2013
Solar project IC-284, Bulloch County
Solar
20.0 MWWithdrawn / abandoned Bulloch, GASoutheast Mar 2013
Solar project IC-289, Clay County
Solar
20.0 MWWithdrawn / abandoned Clay, GASoutheast Apr 2013
Solar project IC-310, Baker County
Solar
20.0 MWWithdrawn / abandoned Baker, GASoutheast Aug 2013
Solar project IC-285, Montgomery County
Solar
20.0 MWWithdrawn / abandoned Montgomery, GASoutheast Mar 2013
Solar project IC-309, Peach County
Solar
19.8 MWWithdrawn / abandoned Peach, GASoutheast Jul 2013
Solar project IC-311, Taylor County
Solar
19.4 MWWithdrawn / abandoned Taylor, GASoutheast Aug 2013
Solar project IC-318, Terrell County
Solar
19.2 MWWithdrawn / abandoned Terrell, GASoutheast Oct 2013
Solar project IC-295, Taylor County
Solar
19.0 MWWithdrawn / abandoned Taylor, GASoutheast May 2013
Solar project IC-297, Decatur County
Solar
18.9 MWWithdrawn / abandoned Decatur, GASoutheast May 2013
Solar project IC-316, Sumter County
Solar
14.0 MWWithdrawn / abandoned Sumter, GASoutheast Sep 2013
Solar project IC-313, Jefferson County
Solar
14.0 MWWithdrawn / abandoned Jefferson, GASoutheast Aug 2013
Solar project IC-294, Echols County
Solar
10.0 MWWithdrawn / abandoned Echols, GASoutheast Apr 2013
Solar project IC-299, Jeff Davis County
Solar
10.0 MWWithdrawn / abandoned Jeff Davis, GASoutheast May 2013

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)