Solar project IC-286, Wheeler County

Solar project IC-286, Wheeler County is a 20.0 MW solar request withdrawn in the Southeast interconnection queue, in Wheeler County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2013 (completed)
  2. Withdrawn / abandonedJul 2016 (project stopped here)
  3. ConsentedJun 2015 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-286
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
McRae Substation 46 kV bus
Location
Wheeler County, Georgia
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
12 March 2013
Agreement signed
29 June 2015
Withdrawn
July 2016

Location

Marker shows the centre of Wheeler County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Wheeler County