Completed queue projects in Florida (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown201,767 MW
Active in queue1,526 MW12 requests
Agreement signed0.0 MW0 requests
Withdrawn655,532 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

20 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 348A, Calhoun County
Solar Β· FPL
350 MWOperating Calhoun, FLSoutheast Jun 20182023
Solar project 240, Levy County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Levy, FLSoutheast Oct 20182023
Solar project 243, Hardee County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Hardee, FLSoutheast Nov 20182022
Solar project 242, Hernando County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Hernando, FLSoutheast Nov 20182022
Solar project 336A, Santa Rosa County
Solar Β· FPL
74.9 MWOperating Santa Rosa, FLSoutheast Mar 20182024
Solar project 352, St Lucie County
Solar Β· FPL
74.5 MWOperating St Lucie, FLSoutheast Jun 20182022
Solar project 360A, Calhoun County
Solar Β· FPL
74.5 MWOperating Calhoun, FLSoutheast Oct 20182023
Solar project 350, Putnam County
Solar Β· FPL
74.5 MWOperating Putnam, FLSoutheast Jun 20182023
Solar project 235, Gadsden County
Solar Β· Florida Renewable Partners, LLC
74.5 MWOperating Gadsden, FLSoutheast Jul 20182024
Solar project 361, Manatee County
Solar Β· FPL
74.5 MWOperating Manatee, FLSoutheast Dec 20182022
Solar project 356, Brevard County
Solar Β· FPL
74.5 MWOperating Brevard, FLSoutheast Jul 20182025
Solar project 338, Hendry County
Solar Β· FPL
74.5 MWOperating Hendry, FLSoutheast Mar 20182024
Solar project 337, Hendry County
Solar Β· FPL
74.5 MWOperating Hendry, FLSoutheast Mar 20182024
Solar project 362, Manatee County
Solar Β· FPL
74.5 MWOperating Manatee, FLSoutheast Dec 20182024
Solar project 351, Putnam County
Solar Β· FPL
74.5 MWOperating Putnam, FLSoutheast Jun 20182024
Solar project 355, Brevard County
Solar Β· FPL
74.5 MWOperating Brevard, FLSoutheast Jul 20182024
Solar project 364, Manatee County
Solar Β· FPL
74.5 MWOperating Manatee, FLSoutheast Dec 20182021
Solar project 365, Manatee County
Solar Β· FPL
74.5 MWOperating Manatee, FLSoutheast Dec 20182024
Solar project 348B, Gadsden County
Solar Β· FPL
74.5 MWOperating Gadsden, FLSoutheast Jun 20182023
Solar project 334, St. Lucie County
Solar Β· FPL
74.5 MWOperating St. Lucie, FLSoutheast Feb 20182023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)