🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Solar project 235, Gadsden County

Solar project 235, Gadsden County is a 74.5 MW solar request built and operating in the Southeast interconnection queue, in Gadsden County, Florida, connecting to Duke Energy Florida.

Queue statusOperating
  1. PlanningQueued Jul 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingNov 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
235
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Florida Renewable Partners, LLC
Connection point (POI)
Atwater Substation
Location
Gadsden County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
NRIS and ERIS
Study phase
IA Executed
Queue status
Operational
Entered queue
17 July 2018
Proposed online date
November 2024
Came online
November 2024

Location

Marker shows the centre of Gadsden County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Gadsden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem