Solar project 336A, Santa Rosa County

Solar project 336A, Santa Rosa County is a 74.9 MW solar request built and operating in the Southeast interconnection queue, in Santa Rosa County, Florida, connecting to Florida Power & Light.

Queue statusOperating
  1. PlanningQueued Mar 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
336A
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Alligator Swamp - Shoal River 230 kV
Location
Santa Rosa County, Florida
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
19 March 2018
Proposed online date
March 2024
Came online
March 2024

Location

Marker shows the centre of Santa Rosa County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Santa Rosa County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem