United States βΊ Grid βΊ Interconnection queues βΊ Florida
SOLAR Β· SOUTHEASTSolar project IC-399, Santa Rosa County
Solar project IC-399, Santa Rosa County is a 40.0 MW solar request withdrawn in the Southeast interconnection queue, in Santa Rosa County, Florida, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2014 (completed)
- Withdrawn / abandonedMay 2015 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-399
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Wright - East Bay 115 kV Line
- Location
- Santa Rosa County, Florida
- Technology
- Solar: 40.0 MW
- Total requested
- 40.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 19 November 2014
- Withdrawn
- May 2015
Location
Marker shows the centre of Santa Rosa County; the queue data does not give exact sites.
Other requests in Santa Rosa County
- Solar project 336A, Santa Rosa CountySolar Β· 74.9 MW Β· built
- Solar project 378A, Santa Rosa CountySolar Β· 74.5 MW Β· built
- Solar project IC-680, Santa Rosa CountySolar Β· 74.9 MW Β· withdrawn
- Solar project IC-687, Santa Rosa CountySolar Β· 50.0 MW Β· withdrawn
- Solar project IC-686, Santa Rosa CountySolar Β· 50.0 MW Β· withdrawn
- Solar project IC-667, Santa Rosa CountySolar Β· 40.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem