Completed queue projects in Florida (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown132,015 MW
Active in queue224 MW3 requests
Agreement signed0.0 MW0 requests
Withdrawn388,979 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 14
Gas
1,148 MWOperating FLSoutheast Mar 2016target 2021
Solar project 144A, Hamilton County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Hamilton, FLSoutheast May 20162018
Solar project 160, Gilchrist County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Gilchrist, FLSoutheast Dec 20162019
Solar project 152, Columbia County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Columbia, FLSoutheast Jul 20162021
Solar project 148, Columbia County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Columbia, FLSoutheast May 20162020
Solar project 158, Hamilton County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Hamilton, FLSoutheast Sep 20162021
Solar project 169, Columbia County
Solar Β· FRP Columbia County Solar, LLC
74.5 MWOperating Columbia, FLSoutheast Dec 20162024
Solar project 174, Gilchrist County
Solar Β· Florida Renewable Partners, LLC
74.5 MWOperating Gilchrist, FLSoutheast Dec 20162024
Solar project 154, Gilchrist County
Solar Β· Florida Renewable Partners, LLC
74.5 MWOperating Gilchrist, FLSoutheast Aug 20162023
Solar project 206, Hendry County
Solar Β· FPL
74.5 MWOperating Hendry, FLSoutheast Sep 20162022
Solar project 173, Levy County
Solar Β· Florida Renewable Partners, LLC
74.5 MWOperating Levy, FLSoutheast Dec 20162025
Solar project 203, Brevard County
Solar Β· FPL
74.5 MWOperating Brevard, FLSoutheast Sep 20162021
Solar project 149, Highlands County
Solar Β· Duke Energy Florida, LLC
45.0 MWOperating Highlands, FLSoutheast Jun 20162019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)