United States โ€บ Grid โ€บ Interconnection queues โ€บ Delaware

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Delaware

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown10317.6 GW
Active in queue874 MW16 requests
Agreement signed50.0 MW3 requests
Withdrawn10317.6 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

103 requests ยท page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore wind project AH1-384, Sussex County
Offshore wind
1,410 MWWithdrawn / abandoned Sussex, DEPJM Sep 2021target 2027
Offshore wind project AH1-278, Sussex County
Offshore wind
1,035 MWWithdrawn / abandoned Sussex, DEPJM Sep 2021target 2027
Offshore wind project AH1-277, Sussex County
Offshore wind
1,035 MWWithdrawn / abandoned Sussex, DEPJM Sep 2021target 2027
Offshore wind project AG2-348, Sussex County
Offshore wind ยท US Wind Inc.
898 MWWithdrawn / abandoned Sussex, DEPJM Mar 2021target 2025
Gas project G29, Sussex County
Gas
750 MWWithdrawn / abandoned Sussex, DEPJM May 2001
Coal project Q42, Sussex County
Coal
630 MWWithdrawn / abandoned Sussex, DEPJM Jun 2006target 2011
Gas project H16, New Castle County
Gas
565 MWWithdrawn / abandoned New Castle, DEPJM Dec 2001target 2005
Gas project J03, New Castle County
Gas
565 MWWithdrawn / abandoned New Castle, DEPJM Sep 2002target 2005
Gas project D15, New Castle County
Gas
550 MWWithdrawn / abandoned New Castle, DEPJM Jul 2000
Offshore wind project R38, Sussex County
Offshore wind
547 MWWithdrawn / abandoned Sussex, DEPJM Nov 2006target 2010
Offshore wind project AG2-108, Sussex County
Offshore wind
460 MWWithdrawn / abandoned Sussex, DEPJM Jan 2021target 2026
Garrison Energy Center
Gas
451 MWWithdrawn / abandoned New Castle, DEPJM Feb 2015target 2024
Offshore wind project R37, Sussex County
Offshore wind
450 MWWithdrawn / abandoned Sussex, DEPJM Nov 2006target 2014
Gas project A61, New Castle County
Gas
450 MWWithdrawn / abandoned New Castle, DEPJM Mar 1999
Bluewater Wind - Bethany
Offshore wind
450 MWWithdrawn / abandoned DEPJM Nov 2006target 2018
Offshore wind project AG2-347, Sussex County
Offshore wind ยท US Wind, Inc
449 MWWithdrawn / abandoned Sussex, DEPJM Feb 2025target 2025
Offshore wind project AG1-087, Sussex County
Offshore wind
440 MWWithdrawn / abandoned Sussex, DEPJM Jul 2020target 2026
Offshore wind project AF2-193, Sussex County
Offshore wind ยท GSOE I, LLC
440 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2026
Offshore wind project AG2-342, Sussex County
Offshore wind
440 MWWithdrawn / abandoned Sussex, DEPJM Mar 2021target 2026
Offshore wind project AF2-194, Sussex County
Offshore wind ยท GSOE I, LLC
440 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2026
Gas project W3-172, New Castle County
Gas
402 MWWithdrawn / abandoned New Castle, DEPJM Oct 2010target 2013
Gas project X2-066, Sussex County
Gas
312 MWWithdrawn / abandoned Sussex, DEPJM Jul 2011target 2016
Gas project X2-067, Kent County
Gas
309 MWWithdrawn / abandoned Kent, DEPJM Jul 2011target 2016
Gas project X3-014, Sussex County
Gas
300 MWWithdrawn / abandoned Sussex, DEPJM Aug 2011target 2016
Edge Moor Units EM6, EM7; Hay Road Units 5,6,7,8
Gas
291 MWWithdrawn / abandoned New Castle, DEPJM Apr 2011target 2018
Gas project A23, New Castle County
Gas
257 MWWithdrawn / abandoned New Castle, DEPJM Oct 1998
Offshore wind project AB1-057, Sussex County
Offshore wind
252 MWWithdrawn / abandoned Sussex, DEPJM Aug 2015target 2020
Gas project T40, Kent County
Gas
225 MWWithdrawn / abandoned Kent, DEPJM Sep 2007target 2012
Gas project W3-173, New Castle County
Gas
218 MWWithdrawn / abandoned New Castle, DEPJM Oct 2010target 2015
Gas project D14, New Castle County
Gas
190 MWWithdrawn / abandoned New Castle, DEPJM Jul 2000
Offshore wind project AE1-118, Sussex County
Offshore wind
152 MWWithdrawn / abandoned Sussex, DEPJM Sep 2018target 2022
Offshore wind project AE1-117, Sussex County
Offshore wind
152 MWWithdrawn / abandoned Sussex, DEPJM Sep 2018target 2022
Battery storage project AG2-271, Sussex County
Battery storage
150 MWWithdrawn / abandoned Sussex, DEPJM Mar 2021target 2023
Offshore wind project AE2-257, Sussex County
Offshore wind
120 MWWithdrawn / abandoned Sussex, DEPJM Mar 2019target 2022
Solar + storage project AG1-497, Kent County
Solar + storage ยท Morgan Branch Solar I, LLC
120 MWWithdrawn / abandoned Kent, DEPJM Sep 2020target 2023
Solar project AG1-061, Sussex County
Solar ยท Deere Acres Solar LLC
109 MWWithdrawn / abandoned Sussex, DEPJM Jul 2020target 2021
Solar project AB2-130, Sussex County
Solar
85.0 MWWithdrawn / abandoned Sussex, DEPJM Apr 2016target 2019
Solar project AB2-187, Sussex County
Solar
80.0 MWWithdrawn / abandoned Sussex, DEPJM Apr 2016target 2017
Solar project AA2-176, Sussex County
Solar
80.0 MWWithdrawn / abandoned Sussex, DEPJM Apr 2015target 2016
Gas project AA1-033, New Castle County
Gas
80.0 MWWithdrawn / abandoned New Castle, DEPJM Jul 2014target 2018
Solar project AF2-385, Sussex County
Solar
75.0 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2022
Battery storage project AH1-761, New Castle County
Battery storage ยท Freepoint Solar LLC
71.0 MWWithdrawn / abandoned New Castle, DEPJM target 2029
Offshore wind project AH1-634, Sussex County
Offshore wind ยท US Wind, Inc
68.0 MWWithdrawn / abandoned Sussex, DEPJM Feb 2025target 2024
Solar project AE1-107, New Castle County
Solar
53.1 MWWithdrawn / abandoned New Castle, DEPJM Sep 2018target 2021
Battery storage project AF2-207, Sussex County
Battery storage
50.4 MWWithdrawn / abandoned Sussex, DEPJM Mar 2020target 2022
Battery storage project AG1-464, Kent County
Battery storage
50.0 MWWithdrawn / abandoned Kent, DEPJM Sep 2020target 2023
Solar project AH1-585, Sussex County
Solar ยท RWE Solar Development, LLC
50.0 MWWithdrawn / abandoned Sussex, DEPJM Jan 2025target 2024
Solar project AH1-584, Sussex County
Solar ยท RWE Solar Development, LLC
50.0 MWWithdrawn / abandoned Sussex, DEPJM Jan 2025target 2024
Battery storage project AH1-586, Sussex County
Battery storage ยท RWE Solar Development, LLC
45.0 MWWithdrawn / abandoned Sussex, DEPJM Jan 2025target 2024
Gas project X1-047, New Castle County
Gas
40.0 MWWithdrawn / abandoned New Castle, DEPJM Mar 2011target 2011
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)