BATTERY STORAGE Β· PJM

Battery storage project AG2-271, Sussex County

Battery storage project AG2-271, Sussex County is a 150 MW battery storage request withdrawn in the PJM interconnection queue, in Sussex County, Delaware, connecting to DPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-271
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DPL
Connection point (POI)
Indian River 230 kV
Location
Sussex County, Delaware
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
19 March 2021
Proposed online date
December 2023
Withdrawn
December 2024

Location

Marker shows the centre of Sussex County; the queue data does not give exact sites.

Power plants in Delaware Β· Transmission lines in Delaware

Other requests in Sussex County